North Yorkshire Council
Executive
13 May 2025
A59 Kex Gill Highway Diversion Update
Report of the Corporate Director of Environment
Appendix A to this report contains exempt information as defined in paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972 as amended by the Local Government (Access to Information)(Variation) Order 2006
1.0 PURPOSE OF REPORT
1.1 To provide a contractual update on the A59 Kex Gill highway diversion works in progress.
1.2 To request increased budget for the project along with a further risk contingency budget.
2.0 SUMMARY
2.1 The A59 project has been in construction delivery since February 2023 when mobilisation commenced; now just over halfway complete, substantial progress has been made, while also experiencing issues leading to an emerging outturn forecast estimated to be above the original risk contingency allocation. This report sets out that while works have continued in terms of the construction, compensation events have arisen which increase the cost of the project. The key reasons being:
§ Late contract entry due to delayed Full Business Case by grant funding body
§ a fundamental change in the design from a Piling to an Earthworks solution,
§ the completion of watercourse design to meet environmental regulations and
§ substantial areas of poor ground being encountered that cannot be incorporated into the finished works requiring export off site and conversely filling with suitable imported classification materials.
2.2 These issues are leading to claims for Compensation Events (CEs) for extra over works under the contract. To ensure sufficient budget is available along with project risk contingency, increased Council sourced match funding is required following additional grant support avenues being declined by the Department for Transport (DfT). To ensure validated CEs are funded within contractually determined timeframes, thus de-risking Council exposure to further claims, approval is requested for additional funding, to ensure necessary additional works continue uninterrupted on site in parallel with original scope and are commercially financially covered.
3.0 BACKGROUND
3.1 The A59 is a key trans-Pennine highway corridor, subject to a long history of land instability and slippage above and below the A59’s southern flank, to the west of Blubberhouses at Kex Gill. Short to medium term management measures are continually being undertaken which has remediated 15 landslides in the last two decades at a cost of c£6m.The latest event was over the 2025 New Year period when the A59 was closed for five weeks while engineering repairs were enacted; the third such closure necessitated during the live capital project works in progress. Significantly the previous landslip and closure in the first half of 2024 cost in the region of £2.8m to repair. In this respect there is an ongoing risk of further costs being incurred to keep the existing A59 open until it its closed permanently when this section of highway is diverted to the new road. Without the capital works there would be a significant risk to the Council if the existing A59 was sought to be remediated for in perpetuity, including the risk of high value injury accident claims, which could exceed direct works costs should a landslip be the reason.
3.2 The works represent the largest capital highway project ever undertaken by the former County Council (NYCC) and now North Yorkshire Council (NYC). It comprises a 4km highway diversion to the northern (stable) side of Kex Gill valley, a 27.8 hectare working site,12 new structures including two underpasses, walls and culverts, 4km new bridleways, 7km of dry stone walling works, 9km of new drainage, two new surface water outfall reservoirs, diversion of Hall Beck, 12km of utility diversions, c370,000m3 of earthworks excavated, the permanent closure of existing A59 reverting back to moorland along works parallel length and planting of c12,000 new trees/shrubs on completion and a new wetland habitat.
3.3 The project gained entry to the Department of Transport (DfT) Major Roads Network (MRN) Programme in February 2021 and following return of construction tenders NYCC Executive on 19 July 2022 resolved: The award of the procurement to the successful tenderer be approved, subject to receipt of the DfT funding and statutory processes being completed, including the full financial assessment of the preferred bidder. Executive approved a funding allocation of £12.7m from the Council.
3.4 On 02 February 2023 the Full Business Case (FBC) was approved by DfT with a grant award of £56.1m, completing the necessary funding source approvals to enable continuation into main construction delivery, however of note this approval was over three months later than anticipated.
3.5 The project was the first nationwide to gain DfT FBC approval from within their wider £1.4billion MRN portfolio and the first to commence works on site. This achievement at the time attracted significant publicity for the Council when the project was formally confirmed by TV media coverage of a Ministerial visit in February 2023 to announce the award.
3.6 Executive Members meeting for Highways and Transportation on 21 December 2022 under delegation conferred by Executive (19 July 2022) approved a report which recognised the delayed DfT FBC approvals and to mitigate against programme interruption proceed with expenditure of Council match funding at risk until the full grant funding award was confirmed. This early match was recouped and to date no Council match funding has been utilised, with call off on NYC allocation not forecast until 2026/27 when the grant funding is exhausted.
3.7 Following a procurement exercise the Council awarded an Advance Works contract on 20 October 2022 and subsequent main works construction contract to the successful tenderer: JJohn Sisk & Son (Holdings) Ltd, a tier one contractor in the UK/Ireland and European Civil Engineering markets on 16 June 2023. The same contractor had delivered significant highway works recently for Leeds City Council/West Yorkshire Combined Authority and is currently engaged upon York Central and Station gateway development establishing a large portfolio regionally.
3.8 Progress on site has been positive and delayed start aside, is largely to the updated programme with the main structures visible from A59 roadside complete to divert the beck, introduce bridleway underpasses and retain the hillside adjacent new road alignment at top of valley. New bridleway paths are near complete with c5km of new drystone walling, drainage outfall holding ponds complete and major earthworks cut and fill operation along the full length is reaching a position where subgrade profiling is complete; this season’s activity will focus upon above ground surface layer works, new embankments, utility diversions and highway subbase.
4.0 DETAIL OF THE ISSUES SUBSTANTIATING THIS REQUEST
4.1 The construction works are being enacted via industry standard New Engineering Contract (NEC) three, Engineering and Construction Contract (ECC) Option A, which is lump sum priced based upon completed activities of work. This cost buildup at tender was across 27 individually priced activities, contained in the Department for Transport (DFT) Manual of Contract Documents for Highway Works (MCHW). While the project is priced as an all-in lump sum including an inflation risk, the Contractor can via a Compensation Event (CE) process seek additional payment for contractor’s extra time and/or costs for dealing with unexpected changes. This also applies to the Consultant support engaged upon the project, who via their Professional Services Contract can seek recompense for costs above the original scope of commission or duration.
4.2 An NEC programme plays a crucial role in project management within the context of the NEC three ECC form of contract, and the primary aim of an Accepted Programme is to encourage effective project management by ensuring that all parties involved understand their responsibilities and deadlines. It also facilitates the timely assessment of CEs (such as extensions of time) during the project. At tender the submitted programme was for a duration of 113 weeks commencing in January 2023 culminating in a March 2025 new highway opening followed by phase 2 decommissioning existing A59/Landscaping of the works up to November 2025. The current accepted contract programme moves the new road opening to June 2026 and a completion of the Phase two works in March 2027.
4.3 An increased programme duration on site in turn increases the works costs, underwritten by the Preliminary Item cost incurred by the contractor establishment overheads due weekly; in this case at tender the original duration overhead was for the 113 weeks only, meaning programme prolongation will increase whole contract cost, as a baseline position before pricing the actual increased additional applicable direct works. The project baseline funding profile contained a risk allocation of £6.390m to capture increased costs from both Contractor and Consultant. In early April 2025 as the contract neared its halfway point this risk reserve had been expended against validated CEs to almost the full allocation amount, leaving the project without continued contingency float to mitigate against ongoing CE derived change.
4.4 Under the contract, CEs have specified response periods, with several in the CE register requiring responses in April and May 2025. Given the urgent nature of these contract events and risk to the Council conferred by non-responses, a Delegated Decision report for urgent top up funding was raised for consideration by the Corporate Director of Resources on 16 April 2025. This action was in line with approval at Executive 20 August 2024 to draw down on the Capital Supply Chain Reserve delegated to the Corporate Director of Resources, in consultation with the Assistant Chief Executive Legal and Democratic Services and the Executive Member for Finance. This action released increased funding of £2m to address timely expedient CEs of an estimated £1.3m, whilst also providing an ongoing float of risk monies of an estimated £700k as a working contingency. A wider outlook determines a further increase in budget is required above the delegated advance noted, to fund pending large value CEs; these details are contained in the commercially confidential Appendix A, along with estimated future costs that could potentially be incurred.
4.5 The agreed and pending CEs are drawing upon the risk allocation at a higher and quicker rate than originally envisaged and can be divided into four categories: contract change; statutory obligations; ground conditions; and design change. Furthermore, this is leading to increased consultancy support required both in resource intensity and increased durations implicating a higher forecast spend on consultancy support.
4.6 Compensation Events have arisen due to the following reasons:
· Contract Change: The first CE was associated with the late confirmed funding award from DfT following a delay to Full Business Case approval. An Advanced Works contract had to be entered into to ensure key seasonal activities were undertaken ensuring a full year’s delay did not occur, but planned programme disruption was still experienced with the late start affecting planned earthworks timetable and therefore resulting in additional costs.
· Statutory Obligation: this related to Hall Beck water course redesign following a requirement to comply with Planning Conditions and Environment Agency notices.
· Ground Conditions: Poor ground has been encountered in several locations across the site, which has required removal and replacement with load bearing material. To mitigate this unpredictable risk against potential high contractor's pricing in the tender, poor ground is an Employer’s risk.
· Design Change: Throughout the construction programme, the design has continued to be developed and optimised against changing conditions on site, ensuring robust high quality and adaptable engineering. Significantly the design has changed from a piled solution to an earth-reinforced embankments solution.
4.7 To date a total of £6.439m has been paid in Compensation Events and these can be categorised in Table 1 below as follows:
Table 1
Category |
Amount |
Earthworks |
£1.728m |
Design Change |
£2.080m |
Contract Change/Award Delay |
£2.463m |
Smaller Compensation Events (various) |
£0.168m |
Total |
£6.439m |
4.8 The project still has a main works programme duration of 14 months to run under a sectional completion phase, targeting new road opening in late June 2026, followed by a final completion phase to extinguish the existing affected A59 and carry out landscaping through to March 2027. During this period further CEs may come to the fore from both Contractor and Consultants, thus increased funding of £11.7m is sought to fund known current CEs in the validation process which includes £1.5m for additional costs from the Council’s design and management consultant due to the prolongation of the scheme programme; and an additional contingency allowance for potential pending CEs forecast as the scheme continues is also outlined in Appendix A. This increased funding would be in addition to the £2m already released from the Capital Supply Chain Reserve and discussed in section 4.4 to address urgent CEs. Appendix A contains commercially sensitive information to inform this forecast outturn.
5.0 CONSULTATION UNDERTAKEN AND RESPONSES
5.1 Consultation has been undertaken with the Department for Transport across two letter correspondences dated 19 January 2024 and 28 May 2024; a request for additional grant funding support was declined by Guy Opperman MP the former Minister for Roads and Local Transport in both instances reasoning ‘As the Kex Gill scheme is currently under construction we consider that the local authority has already clearly demonstrated that is able to secure the funds required and meet the cost risk, as part of the overall costs of the scheme and in addition to the department’s substantial financial contribution’.
5.2 The project position has been reported to the Corporate Management Board, Council Kex Gill Project Board, Highways and Infrastructure Capital Board and Corporate Capital Programme Board, prior to the preparation of this report to Executive.
6.0 CONTRIBUTION TO COUNCIL PRIORITIES
6.1 Whilst short to medium term management measures are continually being undertaken, the Council recognises that in the longer term there was a need to develop proposals for a permanent solution. This requires a major realignment of the route. As such, improvements to the A59 at Kex Gill are identified within the Council’s Local Transport Plan and Strategic Transport Prospectus.
6.2 The project features in the Council Plan 2024 – 2028 and on page 6 contains both a narrative and photograph highlighting it as a Council priority project. Of the 5 key visions and ambitions the project supports Place and Environment ‘a well-connected and planned place with good transport links and Economy ‘new and existing business can thrive and grow’. This key East / West route’s road closures due to land slippage create journey unreliability, while highway safety is a key factor, resilience is also to the fore as, an A59 diversion implicates a 20-mile cross county meander into the Yorkshire Dales network or neighboring Authorities’ towns Otley / Ilkley, all of which add considerable journey time disruption.
7.0 ALTERNATIVE OPTIONS CONSIDERED
7.1 There are no alternative options as the additional costs associated with any validated CEs are due to the contractor under the terms of the contract.
8.0 IMPACT ON OTHER SERVICES/ORGANISATIONS
8.1 Over the duration of the works the A59 has been closed three times due to land slips; between February and June 2024 and the latest 5 weeks across New Year 2025. During the longer closure of February to June 2024, some local businesses made claims for business rates reductions to the Valuation Office. The recent road closure highlighted premium collaborative working required between Comms & media, Highway Operations Area team and the Major Projects Capital team to co-ordinate remedial and closure/diversion efforts.
9.0 FINANCIAL IMPLICATIONS
9.1 The total agreed budget for the project is £68.8m with £56.1m of this being funded by grant from the DfT and the remaining £12.7m being funded from Council reserves.
9.2 The A59 Kex Gill Road Scheme project has been in delivery since February 2023 when site clearance commenced. In the intervening time, progress has been made on the ground, while in parallel we are continuing to experience increased commercial positioning from the contractor and consultant partners as set out in the confidential appendix E to the Q1 Capital Report to Executive of 20 August 2024. This report highlighted that this development led to an outturn forecast in excess of the agreed budget. In order to ensure project continuity through to completion, in light of DfT declining to increase grant support, additional Council funding was required. The report of 20 August 2024 granted delegated approval to the Corporate Director Resources, in consultation with the Assistant Chief Executive Legal and Democratic Services and the Executive Member for Finance to draw down on the totality of the Supply Chain Reserve to fund cost overruns on this scheme. This delegation was utilised on 16 April 2025 in a report to the Corporate Director Resources which approved release of additional urgent project funding of £2m in line with the delegation of the Executive meeting, 20 August 2024 from the Capital Supply Chain Reserve in order to agree contractual time-critical compensation event costs estimated at £1.3m, along with estimated contingency funding of £700k ahead of this report being prepared for the Executive meeting on 13 May 2025.
9.3 The original project budget contained a risk allocation of £6.390m to fund the increased costs resulting from CEs from both Contractor and Consultant. As of 16 April 2025, £6k of this budget remained and it was necessary for this to be increased via a delegated decision of the Corporate Director, Resources as set out above. The agreed compensation events to date total £6.439m and can be divided into categories as follows:
Table 2
Category |
Amount |
Earthworks |
£1.728m |
Design change |
£2.080m |
Contract change |
£2.463m |
Various smaller CEs |
£0.168m |
Total |
£6.439m |
9.4 In addition to the list above, the time critical compensation events due in April prior to the consideration of this report, that required the urgent funding, totalled an estimated £1.3m. This funding was approved as part of the delegated decision report of 16 April 2025.
9.5 Following on from the urgent decision, additional funding is now required to provide financial cover for:
· Necessary changes and improvements to the design and the associated construction costs
· To accommodate the additional work associated with increased areas of poor ground encountered on site and exporting material off site, not originally covered.
· Contractual commercial cover necessary to progress the project, keep to DfT timescales and ensure the approved programme’s critical path is maintained in cognisance of Environmental / seasonal constraints mitigating impact on planned completion dates.
· To keep a contingency float, against risk register for CEs towards works completion.
9.6 The estimated total of the additional CE costs which need to be agreed is £10.2m (in addition to the £2m already agreed in the urgent decision report). There are also additional costs being incurred by the Council’s design and management consultant on the project. It is therefore proposed that a contingency budget of £1.5m is established in relation to these costs.
9.7 This report sets out in Appendix A the detail of the Compensation Event (CEs) costs incurred on the scheme to date, the breakdown of the estimated value of the further CEs which need to be agreed (total - £10.2m), the rationale for the additional costs that are being incurred, the details of the increased consultants costs (£1.5m) along with an estimate of the additional budget required for the remainder of this year. This gives a forecast of the total budget required as a live update while acknowledging the outturn project costs will continue to be refined as the works progress.
9.8 A large proportion of the implemented CEs are due to programme delays at works mobilisation and compliance with statutory obligations. However, pending CEs are principally due to design change that has taken place following the commencement of the scheme. More work is still needed to understand the nature of all the costs, including the total amount that should be sought to be met by the contractor as a contractor risk or by the designer as a design risk. A latent risk also remains that unknown future additional CEs may also require further project funding support as the works progress on site if any further significant engineering problems are encountered or there are delays due to elements for which the council carries the risk such as weather delays.
9.9 In summary, at this stage, in addition to the £2.0m released from the Capital Supply Chain Reserve in April 2025, additional funding of £11.7m is required to fund the implementation of CEs above the existing risk contingency and additional consultant costs to enable the works programme to continue along with the establishment of a risk contingency as set out in Appendix A. However, a latent risk remains that currently unknown future CEs may necessitate further project funding support as the works progress on site if any more significant engineering problems are encountered.
9.10 Further requests for financial support cannot therefore be ruled out at this stage.
10.0 LEGAL IMPLICATIONS
10.1 NYC entered an NEC3 ECC Option A contract for the A59 Kex Gill project, under which Compensation Events can be submitted by the Contractor. The Compensation Events detailed in this reports Appendix A have been assessed by the project team under the provisions of the contract.
11.0 EQUALITIES IMPLICATIONS
11.1 Consideration has been given to the potential for any adverse equalities impacts arising from the recommendations of this report. It is the view of officers that the recommendations included in this report do not have an adverse impact on any of the protected characteristics identified in the Equalities Act 2010. However, it is worth noting that a full Equalities Impact Assessment has been carried out as part of the scheme development and planning application. A copy of the EIA is attached in Appendix B.
12.0 CLIMATE CHANGE IMPLICATIONS
12.1 There are no climate change issues arising from this report; however, it should be noted the projects strategic focus of diverting the highway away from climate perpetuated landslides mitigates against future climate impact on this principal highway corridor. A copy of the initial assessment is attached in Appendix C.
13.0 RISK MANAGEMENT IMPLICATIONS
13.1 Section 4 above covers in detail the risk management implications which are the rationale for the report’s recommendations.
14.0 HUMAN RESOURCES IMPLICATIONS
14.1 An increase in staffing resource is required to facilitate the escalating contractual demand and works prolongation, to be managed by consultant outreach and internal Major Project team attention.
15.0 ICT IMPLICATIONS
15.1 The contract utilises a NEC project management software called CEMAR, (Contract Event Management and Reporting) which is licenced for the duration of the works and is the portal for all formal communication. The increased works duration implies a longer licence period requirement and cost increase.
16.0 COMMUNITY SAFETY IMPLICATIONS
16.1 The project seeks to improve highway safety by delivering safe passage through the Kex Gill valley on this high Pennine pass, against a catalogue of landslides and a poor accident record including fatalities.
17.0 CONCLUSIONS
17.1 Project continuity is at risk due to commercial pressure being experienced with works delivery; in this respect the baseline risk monies allowance is now insufficient to contain cost increases and therefore consideration is being sought towards increasing the Council's capital allocation, following DfT declining to increase grant funding support.
18.0 REASONS FOR RECOMMENDATIONS
18.1 The Council has entered contract under NEC 3 ECC terms which allows risk to be apportioned between the signatures. Delayed start, Statutory obligations, ground conditions and design change on site have contributed to costs escalating beyond the risk attributed to the project at time of tender. Although that risk has now occurred in several instances the Employer will only pay for the actual cost to remedy. It would have been much more expensive should the Contractor have priced for this risk at time of tender. Although various mitigating solutions have been examined the route that offers best value is considered to be a continuation of the contract in its current form, while applying the necessary contractual resourcing as required and completion of the scheme in the shortest time. Given the project is essentially half built, continuing through to completion predominates requiring an increased budget to ensure additional costs arising from the project can be funded.
19.0
19.1 |
RECOMMENDATIONS It is recommended that Members of Executive:
|
|
i) note the contractual position being experienced in delivery of the A59 Kex Gill highway diversion: ii) approve release of additional project budget from the Capital Supply Chain Reserve totalling £11.7m, plus an allowance for a further risk contingency funding as described in confidential appendix A and delegate release of the risk contingency from the Capital Supply Chain reserve to the Corporate Director of Resources in consultation with Corporate Director of Environment and the Assistant Chief Executive Legal and Democratic Services. |
|
|
APPENDICES:
Appendix A – Commercial sensitive information - confidential
Appendix B – Equality Impact Assessment(s)
Appendix C – Climate Impact Assessment(s)
BACKGROUND DOCUMENTS
A59 Kex Gill Executive Committee report 19 July 2022
A59 Kex Gill Executive Committee report 21 December 2022
A59 Kex Gill Executive Members report 28 February 2023
A59 Kex Gill Full Business Case 8 Sept 2022
A59 kex Gill Advance works contract 20 Oct 2022
A59 Kex Gill Main works contract 16 June 2023
A59 Kex Gill DfT Quarterly returns
A59 Kex Gill DfT letter correspondence 19 Jan 2024/28 May 2024
A59 Kex Gill Delegated Decision Report Corporate Director of Resources 16 April 2025
Corporate Director – Karl Battersby
County Hall
Northallerton
2 May 2025
Report Author – Richard Binks – Head of Major Projects and Infrastructure
Presenter of Report – Richard Binks – Head of Major Projects and Infrastructure
Commercial sensitive information (confidential)
Initial equality impact assessment screening form
This form records an equality screening process to determine the relevance of equality to a proposal, and a decision whether or not a full EIA would be appropriate or proportionate.
|
|||||||
Directorate |
Environment |
||||||
Service area |
H&T |
||||||
Proposal being screened |
A59 Kex Gill – progress update and requested increase capital funding. |
||||||
Officer(s) carrying out screening |
Richard Binks |
||||||
What are you proposing to do? |
The report provides a report on the A59 Kex Gill highway project, specifically an update on funding profiling.
|
||||||
Why are you proposing this? What are the desired outcomes? |
This is required to ensure project continuity. |
||||||
Does the proposal involve a significant commitment or removal of resources? Please give details. |
The adjustment to NYC spend profile increases project match funding in years 25/26 through to completion in 29/30
The overall project baseline cost estimate of £68.8m split £56.1m grant funding from DfT and match contribution from NYC Capital Reserves at £12.7m. This report seeks to increase the risk contingency allocation of this funding profile. |
||||||
Impact on people with any of the following protected characteristics as defined by the Equality Act 2010, or NYCC’s additional agreed characteristics As part of this assessment, please consider the following questions: · To what extent is this service used by particular groups of people with protected characteristics? · Does the proposal relate to functions that previous consultation has identified as important? · Do different groups have different needs or experiences in the area the proposal relates to?
If for any characteristic it is considered that there is likely to be an adverse impact or you have ticked ‘Don’t know/no info available’, then a full EIA should be carried out where this is proportionate. You are advised to speak to your Equality rep for advice if you are in any doubt.
|
|||||||
Protected characteristic |
Potential for adverse impact |
Don’t know/No info available |
|||||
Yes |
No |
||||||
Age |
|
X |
|
||||
Disability |
|
X |
|
||||
Sex |
|
X |
|
||||
Race |
|
X |
|
||||
Sexual orientation |
|
X |
|
||||
Gender reassignment |
|
X |
|
||||
Religion or belief |
|
X |
|
||||
Pregnancy or maternity |
|
X |
|
||||
Marriage or civil partnership |
|
X |
|
||||
NYCC additional characteristics |
|||||||
People in rural areas |
|
X |
|
||||
People on a low income |
|
X |
|
||||
Carer (unpaid family or friend) |
|
X |
|
||||
Does the proposal relate to an area where there are known inequalities/probable impacts (e.g. disabled people’s access to public transport)? Please give details. |
No. |
||||||
Will the proposal have a significant effect on how other organisations operate? (e.g. partners, funding criteria, etc.). Do any of these organisations support people with protected characteristics? Please explain why you have reached this conclusion. |
No
|
||||||
Decision (Please tick one option) |
EIA not relevant or proportionate: |
ü |
Continue to full EIA: |
|
|||
Reason for decision |
This is a report updating the spend profile for the Kex Gill realignment project and seeking approval for changes to the spend profile and increased spend of NYC reserves.
There are no impacts on people with protected characteristics. It is worth noting that a full Equalities Impact Assessment will be carried out as part of the scheme development and planning application.
|
||||||
Signed (Assistant Director or equivalent) |
Barrie Mason |
||||||
Date |
01/05/2025 |
||||||
Climate change impact assessment
The purpose of this assessment is to help us understand the likely impacts of our decisions on the environment of North Yorkshire and on our aspiration to achieve net carbon neutrality by 2030, or as close to that date as possible. The intention is to mitigate negative effects and identify projects which will have positive effects.
This document should be completed in consultation with the supporting guidance. The final document will be published as part of the decision making process and should be written in Plain English.
If you have any additional queries which are not covered by the guidance please email climatechange@northyorks.gov.uk
Title of proposal |
Major Highways Scheme A59 Kex Gill Diversion |
Brief description of proposal |
Divert A59 highway to address land instability issue. |
Directorate |
ES |
Service area |
Major Projects and Infrastructure |
Lead officer |
Richard Binks |
Names and roles of other people involved in carrying out the impact assessment |
na |
Date impact assessment started |
March 2025 |
Options appraisal Were any other options considered in trying to achieve the aim of this project? If so, please give brief details and explain why alternative options were not progressed.
The project contained in this report underwent an extensive options development phase which saw 16 design configurations evaluated before taking forward the option which delivers the best value, deliverability and engineering outcome to detail design and tendering.
When delivering schemes consultation is carried out with residents and stakeholders to ensure that they are the correct schemes and that a consistent approach is taken to introducing carbon neutral measures within the build landscape and attendant public safety is captured.
|
What impact will this proposal have on council budgets? Will it be cost neutral, have increased cost or reduce costs?
Please explain briefly why this will be the result, detailing estimated savings or costs where this is possible. Impact upon Council Capital financial budget is to the fore; while the project is in receipt of generous grant funding of £56.1million from the Department for Transport (DfT) the whole project cost was originally forecast to be £68.8m. This placed a call for £12.70m from Council Capital reserves. The Delegated report of 16 April 2025 approved £2m additional risk funding. Confidential Appendix A of this report 13 May Executive contains details of wider impact upon Council budget.
No cost increases are directly related to climate change and tendered solutions require a commitment from bidders to demonstrate green credentials, use of local supply chains and resources within their quality bid in association with price.
It was intended that the project will be delivered with the funding that has been offered by the DfT and the originally approved Council funding contribution, however mid project delivery cost profiling now forecasts an exceedance of the risk budget due to delayed start, statutory obligations, ground conditions and design change on site contributing to costs escalating beyond the risk attributed to the project at time of tender.
|
How will this proposal impact on the environment?
|
Positive impact (Place a X in the box below where relevant) |
No impact (Place a X in the box below where relevant) |
Negative impact (Place a X in the box below where relevant) |
Explain why will it have this effect and over what timescale?
Where possible/relevant please include: · Changes over and above business as usual · Evidence or measurement of effect · Figures for CO2e · Links to relevant documents |
Explain how you plan to mitigate any negative impacts.
|
Explain how you plan to improve any positive outcomes as far as possible. |
|
Minimise greenhouse gas emissions e.g. reducing emissions from travel, increasing energy efficiencies etc.
|
Emissions from travel |
X |
|
|
improved network efficiency; less road closures and long diversion routes
|
|
|
Emissions from construction |
|
|
X |
sustainable material supply chains, improved construction plant and company carbon neutral commitments will support cleaner construction activities to minimise the impact of construction activities
|
|
|
|
Emissions from running of buildings |
|
X |
|
na |
|
|
|
Other |
|
X |
|
na |
|
|
|
Minimise waste: Reduce, reuse, recycle and compost e.g. reducing use of single use plastic |
|
X |
|
Recycled material will be incorporated in design and construction as achievable
|
|
|
|
Reduce water consumption |
X |
|
|
Marginal improvements via improved highway drainage and creation of new wetland habitats.
|
|
|
|
Minimise pollution (including air, land, water, light and noise)
|
X |
|
|
Air quality improvements applicable to increased highway network efficiency and resilience
|
|
|
|
Ensure resilience to the effects of climate change e.g. reducing flood risk, mitigating effects of drier, hotter summers |
X |
|
|
Improvement to valley slope stability; reduce risk of landslides.
|
|
|
|
Enhance conservation and wildlife
|
X |
|
|
Projects include comprehensive ecology interventions ranging from creation of wetlands, new coppices, habitat investment, nesting sites and respect of wildlife seasons.
|
|
|
|
Safeguard the distinctive characteristics, features and special qualities of North Yorkshire’s landscape
|
X |
|
|
Project is designed to enhance the natural beauty of NY landscape and follow the natural terrain, while converting the existing highway back to moorland where possible.
|
|
|
|
Other (please state below)
|
|
X |
|
|
|
|
Are there any recognised good practice environmental standards in relation to this proposal? If so, please detail how this proposal meets those standards. |
Project design complies with all current good practice or regulatory guidance / statutes and has undergone a rigorous assessment by the Department for Transport during Business Case development and Planning Permissions to ensure national environmental standards are being adhered to.
|
Summary Summarise the findings of your impact assessment, including impacts, the recommendation in relation to addressing impacts, including any legal advice, and next steps. This summary should be used as part of the report to the decision maker.
Development of this Major Project has encapsulated strategic directives to support proactive climate change features within design and construction. The A59, a strategic east / west principal highway route across the southern region of the county is regularly interrupted by landslides in this valley location high upon the Pennine hill chain (15 since year 2000). Weather events in this remote location feel the full force of increased storm conditions plus intensity, which generate afore noted land instability. The new route will provide additional resilience to anticipated climate change impacts – ie storm, flash floods, which may grow in intensity and frequency in future.
Next steps focus upon completion of the construction works, currently halfway through with a programmed completion of all associated landscape works in March 2027 including decommissioning the existing A59 for a 4km length back to nature and associated off site environmental upgrades agreed under planning conditions.
|
Sign off section
This climate change impact assessment was completed by:
Authorised by relevant Assistant Director (signature): Barrie Mason
Date: 01/05/2025
|