Appendix A  

 

Proposed Schools Condition Capital Programme 2025/26

Amount (£)

 

Potential Capital Funding Available:

 

Capital Planned Maintenance Programme 24/25 carry forward

12,000

General compliance/H&S 24/25 carry forward

148,200

Accessibility Schemes 24/25 carry forward

146,200

Estimated contribution from School’s Devolved Formula Capital (DFC) in 25/26

150,000

General contingency 24/25 carry forward and unallocated

1,218,200

Schools Condition Allocation 25/26

7,029,777

Total Potential Capital Funding Available

8,704,377

 

Capital Maintenance and Compliance/Regulatory Requirements:

 

General Compliance and Health & Safety (£260k + £140k cf)

400,000

Capital Planned Maintenance Programme (£150k DFC contributions + £4.02m)

4,176,560

In year failures

1,500,000

Accessibility Schemes (£146k cf + £24k)

170,000

Glazing Regulation Survey Work

150,000

Asbestos abatement works

250,000

 

 

 

Total Capital Maintenance and Compliance/Regulatory Requirements

6,646,560

 

Proposed Capital Investment – Strategic Priorities:

 

Kitchen Refurbishments

450,000

Drainage works

757,000

Works Arising from School Amalgamation

200,000

 

 

Total Proposed Capital Investment - Strategic Priorities

1,407,000

 

Strategic Support for Capital Projects (Band N post)

67,596

 

Total Proposed Investment

8,121,156

General Contingency / Unallocated

583,221