Risk Trend |
Risk |
Description |
Risk Owner |
Risk Manager |
Curr Prob |
Curr Imp |
Current Risk Score |
Current Category |
Targ Prob |
Targ Imp |
Target Risk Score |
Target Category |
FB Plan? |
|
|
CDE_10 Housing Regulations |
Failure to comply with housing legislation including the Social Housing (Regulation) Act and achieve a satisfactory grade with the Regulator of Social Housing, resulting in injury or ill health of tenants, prosecution with subsequent financial penalty, reputational damage to the council and loss of control of the service. |
CD ComDev |
ComDev AD Hou |
H |
VH |
20 |
Very High |
M |
H |
12 |
Medium High |
|
|
|
CDE_8 Local Plan |
Failure to develop a Local Plan by 2029 as a framework to promote growth and support decision making around planning and development in North Yorkshire resulting in risk of appeals with resulting financial and workload implications adverse implications for the local economy and the Council’s ambitions for growth and place making |
CD ComDev |
ComDev AD Plan |
H |
H |
16 |
High |
M |
H |
12 |
Medium High |
|
|
|
CDE_11 Capital Programme |
Failure to put together a sustainable capital programme including Housing (HRA), Culture, Leisure and Libraries, Regeneration Schemes such as Catterick LUF, Scarborough and Whitby Towns Fund and Harrogate Convention Centre redevelopment resulting in budget overspends, loss of reputation |
CD ComDev |
RES AD (PF) |
M |
H |
12 |
Medium High |
M |
H |
12 |
Medium High |
|
|
|
CDE_12 Harrogate Convention Centre |
Failure to put in place an effective programme for Harrogate Convention Centre reinvestment/redevelopment and agree how the Centre operates in the future resulting in inability to maintain the present order book, missed commercial opportunities and inefficiency |
CD ComDev |
ComDev Dir HCC |
M |
H |
12 |
Medium High |
M |
H |
12 |
Medium High |
|
|
|
CDE_2 Financial Challenges |
Failure to manage the revenue budget due to increased costs, demands and reduced income, together with delivery of transformation savings requirements results in budgetary pressure, missed opportunities and internal / external criticism |
CD ComDev |
RES AD (PF) |
M |
H |
12 |
Medium High |
M |
H |
12 |
Medium High |
|
|
|
CDE_14 Regeneration schemes |
Failure to fund, develop and deliver on key regeneration schemes across the county (eg.Town Deals, Plan for Neighbourhoods, Town Investment Plans, Mayoral Investment Fund and other external funded schemes) resulting in missed opportunities to revitalise target areas |
CD ComDev |
ComDev AD PSG |
M |
H |
12 |
Medium High |
L |
H |
8 |
Medium |
|
|
|
CDE_3 Service integration |
Failure to bring together the existing systems and processes into a single service operating model for NYC results in ineffective and inconsistent approach to operations and decision making, reduced performance, increase in challenge and missed opportunities. |
CD ComDev |
ComDev DMT |
M |
H |
12 |
Medium High |
L |
H |
8 |
Medium |
|
|
|
CDE_6 Health and Safety |
Failure to operate appropriate Health and Safety practice across the Directorate resulting in serious injury to staff and potential prosecution |
CD ComDev |
ComDev DMT |
M |
H |
12 |
Medium High |
L |
H |
8 |
Medium |
|
|
|
CDE_5 Information Governance and Data Security |
Ineffective information governance arrangements leading to unacceptable levels of unauthorised disclosure of personal and sensitive data, vulnerability to cyber-attack and poor quality or delayed responses to FoI requests in the context of merging systems and processes into a single service resulting in impact on service users, loss of reputation, poor decision making and fines |
CD ComDev |
ComDev DMT |
M |
M |
9 |
Medium |
M |
M |
9 |
Medium |
|
|
|
CDE_4 Restructure, Recruitment, Retention and Culture |
Failure to embed team structures, support the convergence of teams with sufficient skilled staff with customer focus and a defined performance framework to deliver quality services. Also the inability to recruit and retain sufficient skilled staff results in sub optimal performance, resourcing issues, increased workload pressures, criticism and missed opportunities including the ability to generate income |
CD ComDev |
HoHR (ComDev) |
M |
M |
9 |
Medium |
L |
M |
6 |
Medium |
|
|
|
CDE_7 Growth |
Failure to deliver the ambition of sustainable economic growth that enables people and places to prosper; new and existing business to thrive and grow; a productive and skilled workforce; culture, heritage, arts and sustainable tourism to all play their part and the County to have a high profile and receive its fair share of resources. This results in an inability to attract, retain and grow businesses, increase the number of strategic employment and housing sites, raise living standards and increase spending power. |
CD ComDev |
ComDev AD PSG |
M |
M |
9 |
Medium |
L |
M |
6 |
Medium |
|
|
Risk Trend Key |
|
|
Symbol |
Meaning |
|
|
Risk ranking has worsened since the last review. |
|
|
Risk ranking is the same as at last review. |
|
|
Risk ranking has improved since the last review. |
|
new |
Risk is new or has been significantly altered since the last review. |