1.0 PURPOSE OF REPORT
1.1 To seek approval from the Corporate Director of Environment, in consultation with the Executive Member for Highways and Transportation, to increase fees and charges for the financial year 2026/27, in line with the Corporate Fees and Charges Strategy.
2.0 BACKGROUND
2.1 Highways and Infrastructure fees and charges were reviewed in 2025 and following a report to the Environment Corporate Director and Environment Executive Member, were increased in line with inflation, or by a greater amount where costs had increased further, for the 2026/27 financial year.
2.2 The Council’s fees and charges policy agreed in November 2022 provides the framework for fees and charges to be reviewed and updated on an annual basis.
2.3 This report seeks approval for a 3.4% increase in fees and charges from 01 April 2026, on fees and charges where a non-statutory charge can be made. This covers the majority of chargeable services.
2.4 The report also seeks approval for the introduction of increased fees and charges for a small number of other chargeable services related to Traffic Regulation Orders (TROs) and the introduction of new charges for carrying out a search of the Street Works Register on behalf of a customer.
2.5 A full summary of fees and charges for 2026/27 is set out in Appendix A of this report.
2.6 For completeness, fees and charges for Highways and Transportation, Parks and Countryside Services are in-scope for this review. Although Parking Services also forms part of the Highways and Infrastructure Service Unit, parking charges are a separate matter and so remain outside the scope of this report.
3.0 METHODOLOGY
3.1 As in previous years, fees and charges have been reviewed in line with the Corporate Fees and Charges Strategy and all fees and charges set out in Appendix A have had a minimum flat rate 3.4% uplift to account for the effects of inflation and pay award projections, unless a greater increase was necessary, eg due to higher industry or input costs. A small number of fees have been rounded to either assist with cash handling; or where fees are calculated per metre, but a minimum charge applies. A limited number of markets and games in parks fees have been discontinued and are referenced in Appendix A.
3.2 It is proposed to introduce a new charge for the supply of information relating to street works is held within the Street Works Register. This is publicly available for inspection. Where a customer requests that the Council undertakes a search of the Street Works Register on their behalf, this will be treated as an Environmental Information Request under the Environmental Information Regulations 2004. In line with the Regulations, the Council may charge a reasonable fee to cover the costs of searching for, retrieving and collating the requested information. Any applicable charge will be confirmed in advance, and work will not commence until the requester has agreed to the fee. It is proposed that a charge of £55.87 per hour is introduced for undertaking this activity.
3.3 Fees associated with Section 50 and Section 171 Licences have been reviewed and benchmarked against other local highway authorities. As a result, the fee for a Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) (including and application and inspection) has increased to £900 (including the statutory inspection fee of £150). An application without inspections will now be £750.
3.4 A further review of fees and charges associated with Temporary Traffic Regulation orders (TTROs) has been carried out against charges from other local highway authorities. Following this review, fees have been increased from £650 to £1200 (plus advertising costs) for 18 month TTROs and £500 to £900 for emergency, five day and temporary event TTROs.
4.0 ALTERNATIVE OPTIONS CONSIDERED
4.1 The Corporate Fees and Charges Strategy requires full cost recovery, which for 2026/27, has been set at a minimum 3.4% uplift. Where a different approach is proposed, it is set out separately in this report and its Appendix A.
5.0 FINANCIAL IMPLICATIONS
5.1 The Corporate Fees and Charges Strategy establishes a requirement to review fees and charges within Directorates on an annual basis, in order to help raise income and lower the burden to Council Taxpayers and ensure that the fee charged for a council service is reflective of the council’s costs of provision.
5.2 The proposed schedule attached as Appendix A does not include all Highways and Infrastructure fees and charges. For areas of the service that have been the subject of more significant cost increases, eg the NYC Permit scheme, detailed cost exercises are currently being carried out to establish the true cost of provision, to ensure fees and charges are set at the right level. The outputs from these more detailed reviews will be presented to a separate Environment Executive Member meeting.
5.3 More generally, this report proposes that Highways and Infrastructure fees and charges estimated income will increase as a result of the proposed prices in Appendix A, which in the main, are due to applied inflation since the previous fee review.
5.4 It is estimated that the increases above inflation, linked to TTROs and S50/S171 works alongside the introduction of the street works register charge will increase income by £412K per annum compared to 2025/26. This income has been identified within the Medium-Term Financial strategy as savings proposals
6.0 LEGAL IMPLICATIONS
6.1 The methodology adopted for increasing fees and charges is consistent with the Corporate Fees and Charges Strategy, which indicated that the Fees and Charging Policy applies to services where there is a legal power to charge for the service and discretionary services.
6.2 Section 93 of the Local Government Act 2003 and Section 3 of the Localism Act 2011 give local authorities power to charge for discretionary services. Discretionary services are those services that a local authority is not required to provide but may do so voluntarily.
6.3 The charging powers do not apply where there is a power to charge for a particular service elsewhere in other legislation, or where other legislation expressly excludes an authority from charging.
7.0 EQUALITIES IMPLICATIONS
7.1 No equalities implications are considered to arise as a result of the proposed changes to the fees and charges set out in Appendix A. Any increase is reflective of the cost of delivering the service and/or in line with the Consumer Price Index inflation rate. All the rates have previously been benchmarked against comparator authorities. An Equalities Impact Assessment screening form has been completed, which is attached as Appendix B.
8.0 CLIMATE CHANGE IMPLICATIONS
8.1 No climate change impact is considered to arise as a result of the proposed fees and charges, see Appendix C for further details.
9.0 REASONS FOR RECOMMENDATIONS
9.1 To ensure that the fee charged for a council service is reflective of the Council’s costs of provision.
|
10.0 |
RECOMMENDATION
|
|
10.1 |
It is recommended that the Corporate Director of Environment, in consultation with the Executive Member for Highways and Transportation, approves:
i. a 3.4% increase in appropriate fees and charges as outlined in Appendix A ii. introduction of a new charge for Streetworks register searches iii. increase in charges for Section 50 and Section 171 Licences and the processing of Temporary Traffic Regulation Orders. |
APPENDICES:
Appendix A: Proposed Fees and Charges Schedule 2026/27 for Highways and Transportation,
Street Scene and Parks and Countryside Services.
Appendix B: Initial Equality Impact Assessment Screening Form
Appendix C: Climate Change Impact Assessment
BACKGROUND DOCUMENTS: None
Barrie Mason
Assistant Director – Highways and Infrastructure
County Hall
Northallerton
Report Author – James Gilroy
Presenter of Report – James Gilroy
Note: Members are invited to contact the author in advance of the meeting with any detailed queries or questions.
|
Title |
Current price |
Proposed New Price |
Comments |
|
Abnormal loads notification |
No fee |
No Fee |
Legislation states no fee applicable |
|
Traffic speed and flow data (where available) Per site. Where non-standard reports are requested this fee will increase. Applicants will be notified prior to charges. Where the request is received from a member of the public and is straightforward the fee may be waived. |
£63.85 |
£66.02 |
|
|
Traffic speed and flow data (where available) per hour (or part hour). Where non-standard reports are requested this fee will increase. Applicants will be notified prior to charges. Where the request is received from a member of the public and is straightforward the fee may be waived. |
£54.03 |
£55.87 |
|
|
Over-sail of the highway by crane and cable spanning the highway applications |
£176.83 |
£182.85 |
|
|
Officer time spent dealing with requests for commercial events on the highway |
£54.04 |
£55.87 |
|
|
Officer time spent dealing with applications from external organisations to carry out traffic surveys on the public highway |
£54.04 |
£55.87 |
|
|
Skip licences two week licence. |
£88.41 |
£91.42 |
|
|
Skip licences Early start fee (if licence is required within 3 days of request). |
£34.39 |
£35.56 |
|
|
Skip licences Failure to comply with the licence conditions will result in a further inspection fee. |
£67.53 |
£69.83 |
|
|
Skip licences No licence extensions. If a skip needs to be in situ for longer than two weeks then an additional fee will apply. |
£88.41 |
£91.42 |
|
|
Skip licences If an un-licensed skip is found on the highway. |
£190.33 |
£196.80 |
|
|
Scaffold / hoarding licences Standard (<10m height) Licence fee (four weeks) |
£244.37 |
£252.68 |
|
|
Scaffold / hoarding licences Standard (<10m height) Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Standard (<10m height) Extension fee |
£108.86 |
£111.73 |
|
|
Scaffold / hoarding licences Non-standard (> 10m height) Licence fee (four weeks) |
£244.37 |
£252.68 |
|
|
Scaffold / hoarding licences Non-standard (> 10m height) Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Non-standard (> 10m height) Extension fee |
£108.86 |
£111.73 |
|
|
Scaffold / hoarding licences Retention scaffold Licence fee (four weeks) |
£487.51 |
£504.08 |
|
|
Scaffold / hoarding licences Retention scaffold Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Retention scaffold Extension fee |
£108.86 |
£111.73 |
|
|
Scaffold / hoarding licences Tower scaffold (if removed daily) Licence fee (four weeks) |
£40.53 |
£41.90 |
|
|
Scaffold / hoarding licences Tower scaffold (if removed daily) Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Tower scaffold (if removed daily) Extension fee |
£20.88 |
£21.59 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway 1.5m+) Licence fee (four weeks) |
£121.57 |
£125.70 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway 1.5m+) Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway 1.5m+) Early start fee |
£108.06 |
£111.73 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway <1.5m) Licence fee (four weeks) |
£244.37 |
£252.68 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway <1.5m) Early start fee |
£34.39 |
£35.56 |
|
|
Scaffold / hoarding licences Hoarding (remaining width of footway <1.5m) Extension fee |
£108.06 |
£111.73 |
|
|
Street café license Application fee Up to 5 tables or Up to 10m2 - plus works costs |
£338.92 |
£350.44 |
|
|
Street café license Application fee Over 5 tables or Over 10 m2 - plus works costs |
£610.30 |
£631.05 |
|
|
Street café license Application fee - Amount non refundable |
£108.06 |
£111.73 |
|
|
Street café license Annual renewal fee Up to 5 tables or Up to 10m2 |
£88.41 |
£91.42 |
|
|
Street café license Annual renewal fee Over 5 tables or Over 10 m2 |
£155.96 |
£161.26 |
|
|
Building materials licence |
£88.41 |
£91.42 |
|
|
Highway projection licence |
£176.83 |
£182.85 |
|
|
Cellar opening licence |
£54.04 |
£55.87 |
|
|
Temporary Traffic Regulation Orders 18-month closure - (plus advertising costs) |
£650.00 |
£1200 |
|
|
Temporary Traffic Regulation Orders five day closure |
£500.00 |
£900 |
|
|
Temporary Traffic Regulation Orders Emergency closure |
£500.00 |
£900 |
|
|
Temporary Traffic Regulation Orders Event closure - for a new event |
£500.00 |
£900 |
|
|
Temporary Traffic Regulation Orders Recurring event (plus advertising at cost) |
£250.00 |
£258.50 |
|
|
Temporary Traffic Regulation Orders Additional charges will be applied where further work is required in relation to a temporary closure at an hourly rate of: |
£54.04 |
£55.87 |
|
|
Rechargeable works admin fee – Damage works Work costs <£500 |
£61.39 |
£63.48 |
|
|
Rechargeable works admin fee – Damage works Work costs £500 - £1,000 |
£122.80 |
£126.967 |
|
|
Rechargeable works admin fee – Damage works Work costs >£1,000 |
25% |
25% |
|
|
Con29 Highway Search, Standard Highway search (VAT included) |
£58.44 |
£60.43 |
|
|
CON29 Highway Search Optional Questions Q4 |
£18.11 |
£18.73 |
|
|
CON29 Highway Search Optional Questions Q21 |
£5.01 |
£5.18 |
|
|
CON29 Highway Search Optional Questions Q22 |
£25.18 |
£26.04 |
|
|
Non-CON29 Highway Enquiry (inc a plan (up to 100m) and CON29 type questions but not in accordance with the Local Authorities (Charges for Property Searches) Regulations 2008 |
£71.89 |
£74.33 |
VAT not applicable |
|
Non-CON29 Highway Enquiry (as above but each additional 100m on a plan) and CON29 type questions |
£34.79 |
£35.79 |
|
|
Non-CON29 Highway Enquiry (not inc a reply plan) - Is the road publicly maintainable highway? or subject to adoption and supported by a bond or waiver?; or to be made up by the local authority who will either reclaim the costs from the frontagers or not reclaim the costs? Discretionary charge as of 1st April 2026 |
£30.56 |
£31.60 |
|
|
Non-CON29 Highway Enquiry (not inc a reply plan) - Is any PRoW which abuts or crosses the property shown on the Definitie Map?; Are there any pending applications to record a PRoW that abuts or crosses the property?; Are there any legal orders to stop-up, divert, alter or create a PRoW which abuts or crosses the property? |
£10.78 |
£11.15 |
|
|
Non-CON29 Highway Enquiry (not inc a reply plan) Is the property to be included in land to be acquired for road works? |
£3.05 |
£3.16 |
|
|
Non-CON29 Highway
Enquiry (not inc a reply plan) Is the property (or will it be)
within 200 metres of any of the following? |
£12.22 |
£12.63 |
|
|
Non-CON29 Highway
Enquiry (not inc a reply plan) Has a local authority approved but
not yet implemented any of the following for the roads, footways
and footpaths which are named in Box B & C and are within 200
metres of the boundaries of the property? |
£12.22 |
£12.63 |
|
|
Non-CON29 Highway
Enquiry (not inc a reply plan) Do any statutory notices which
relate to the following matters subsist in relation to the property
other than those revealed in a response to any other enquiry in
this form? |
£3.05 |
£3.16 |
|
|
Regulation 43 of the Commons Registration (England) Regulations 2014 (Application form CA15) |
£81.17 |
£83.93 |
|
|
Section 6 of the 2006 Act CA1 Creation of a right of common over existing common land |
£342.07 |
£353.70 |
|
|
Section 6 of the 2006 Act CA1 Creation of a right of common over existing common land Creation of a right of common resulting in the registration of new common land |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Section 7 of the 2006 Act CA2, Variation of a right of common |
£342.07 |
£353.70 |
|
|
Section 7 of the 2006 Act, CA2, Variation of a right of common resulting in the registration of new common land |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Section 8 of the 2006 Act CA3, Apportionment of a right of common |
£342.07 |
£353.70 |
|
|
Section 10 of the 2006 Act CA4, Attachment of a right of common |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Section 11 of the 2006 Act CA5 Reallocation of attached rights |
£342.07 |
£353.70 |
|
|
Section 12 of the 2006 Act, CA6, Transfer of a right in gross |
£127.56 |
£131.89 |
|
|
Section 13 of the 2006 Act CA7, Surrender or extinguishment of a right of common |
£255.10 |
£263.77 |
|
|
Section 4, paragraph 8 of the 2006 Act CA8, Statutory disposition pursuant to section 14 of the 2006 act (including the exchange of land for land subject to a statutory disposition) |
£510.20 |
£527.55 |
|
|
Section 15(1) or Section 15(8) of the 2006 Act CA9 Registration of a new town or village green by the owner or someone other than by the owner |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Section 19 of the 2006 Act CA10 Correction, for a purpose described in section 19(2)(d) |
£57.98 |
£59.95 |
|
|
Section 19 of the 2006 Act CA10 Correction, for a purpose described in 19(2)(b) or (e) |
£342.07 |
£353.70 |
|
|
Section 19 of the 2006 Act, CA10 Correction, for a purpose described in Section 19(2)(a) or (c) |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Schedule 1, paragraph 19(6)(b), to the 2006 Act CA11 Severance by transfer to public bodies |
£86.97 |
£89.92 |
|
|
Schedule 1, paragraph 3 (7)(b), to the 2006 Act CA12 |
£255.10 |
£263.77 |
|
|
Schedule 2, paragraphs 6 - 9, to the 2006 Act CA13 Deregistration of certain land registered as common land or as a town or village green |
£1,704.54 |
£1762.50 |
|
|
Schedule 2, paragraph 2 or 3, to the 2006 Act CA13 Non-registration of common land or town or village green |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Schedule 2, paragraph 4, to the 2006 Act CA13, Waste land of a manor not registered as common land |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Schedule 2, paragraph 5, to the 2006 Act CA13 Town or village green wrongly registered as common land |
No Fee |
No Fee |
Legislation states “No fee applicable” |
|
Schedule 3, paragraph 2 or 4, to the 2006 Act CA14 Creation of a right of common, statutory disposition (including the exchange of land for land subject to a statutory disposition) and variation |
£469.62 |
£485.59 |
|
|
Schedule 3, paragraph 2 or 4, to the 2006 Act, CA14, Apportionment of a right of common (to facilitate any other purpose) |
£429.03 |
£443.62
|
|
|
Schedule 3, paragraph 2 or 4, to the 2006 Act CA14 Surrender or extinguishment of a right of common, severance of a right of common, transfer of a right in gross |
£289.89 |
£299.75 |
|
|
Section 15A(1) of the 2006 Act, CA16 Deposits under section 31(6) of the Highways Act 1980 and section 15A(1) of the Commons Act 2006 |
£452.22 |
£467.60 |
|
|
Section 15A(1) of the 2006 Act, CA16 Deposits under section 31(6) of the Highways Act 1980 and section 15A(1) of the Commons Act 2006 (Any additional notices per notices) |
£34.79 |
£35.97 |
|
|
General Enquiry Requesting a copy of a register/ plan |
£18.42 |
£19.05 |
|
|
S38 Superintendence fees, minimum fee for both Section 38 and 278 Agreements £2,000. |
12% |
12% |
Percentage is based on value of the associated bond |
|
S278 Superintendence fees, minimum fee for both Section 38 and 278 Agreements £2,000. |
12% |
12% |
Percentage is based on value of the associated bond |
|
S278 Supervision fees for 278 agreement work where the Highway Development Service has been used |
10% |
10% |
Percentage is based on value of the associated bond |
|
Stopping up order Officer time spent dealing with an application will be charged at an hourly rate as listed. Other external costs incurred by the County Council will be recharged to the applicant. |
£54.04 |
£55.87 |
|
|
Stopping up order Other external costs are also charged to the customers. |
£0.00 |
£.000 |
Direct charge of any external costs |
|
Stopping up order Initial fee the applicant must pay with the initial request, the balance must be settled prior to the application to the Magistrates Court. |
£1,016.76 |
£1051.33 |
|
|
H-Bar Markings |
£271.39 |
£280.61 |
|
|
Request from consultants / private companies for ‘new’ information |
£54.04 |
£55.87 |
|
|
Structures approval Hourly rate of officer time spent assessing new structures proposed by developers |
£54.04 |
£55.87 |
|
|
Structures approval Initial request fee the applicant must pay (the balance must be settled with the request for signature of the Approval in Principle (AIP)) |
£135.08 |
£139.67 |
|
|
Application from developer for a Traffic Regulation Order amendment |
£54.04 |
£55.87 |
|
|
Mobile mechanical plant machinery e.g. cherry picker, scissor lifts and cranes (one day or less) There is no charge for mobile mechanical plant machinery that is on site for one day or less. |
No Fee |
No Fee |
|
|
Mobile mechanical plant machinery e.g. cherry picker, scissor lifts and cranes (more than one day) £144.00 for a two week licence |
£176.83 |
£182.85 |
|
|
Mobile mechanical plant machinery e.g. cherry picker, scissor lifts and cranes (more than one day) Early start fee (if licence is required within three days of request). |
£34.39 |
£35.56 |
|
|
Mobile mechanical plant machinery e.g. cherry picker, scissor lifts and cranes (more than one day) If mobile mechanical plant machinery needs to be in situ for longer than two weeks then an additional weekly extension fee will apply: |
£108.06 |
£111.73 |
|
|
Mobile mechanical plant machinery e.g. cherry picker, scissor lifts and cranes (more than one day) Failure to comply with the licence conditions will result in a further inspection fee of:c |
£67.53 |
£69.83 |
|
|
Tourist Traffic Signs Initial assessment fee (non-refundable). |
£202.61 |
£209.50 |
|
|
Tourist Traffic Signs Additional charges will be applied where further work is required in relation to an application at an hourly rate |
£54.04 |
£55.87 |
|
|
Road safety audits - hourly rate |
£54.04 |
£55.87 |
|
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Total includes and application and inspection. |
£600.00 |
£900.00 |
Includes mandatory 3 x Inspections |
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Licence fee |
£450.00 |
£750.00 |
Does not include mandatory 3 x Inspections |
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Inspection fee x3 |
£150.00 |
£150.00 |
Statutory fee figure |
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Inspection fee (1 unit) 15 working days or less |
£150.00 |
£150.00 |
Statutory fee figure |
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Additional inspection fee (2 units) 16-30 working days |
£300.00 |
£300.00 |
Statutory fee figure |
|
Temporary excavation in the Highway (s171 HA) and licence to place and maintain/repair apparatus in the Highway (s50 NRSWA) Additional inspection fee (3 units) greater than 30 working days |
£450.00 |
£450.00 |
Statutory fee figure |
|
Search of the Street Works Register on behalf of a customer |
New Charge |
£55.87 |
|
|
Commercial application including Temporary Site Accesses that are not part of a S278 Agreement. |
£2000 per access |
£2,068 |
|
|
Dropped Kerb application, using independent contractors from approved contractor list |
£300 licence fee |
£310.20 |
|
|
Quote for dropped kerb to be delivered through HDS |
£99 paid to LHA |
£102.36 |
|
|
Design and Admin Fee to be charged by HDS |
10% of construction quote offered by NYH |
10% of construction quote offered by NYH |
|
|
Pavement Licence |
- |
|
New fee set in statute as part of Pavement Licensing Legislation – work on going |
|
Cost of 1 tonne of salt to be delivered (per tonne). Bulk delivery only |
£150 |
£155.10 |
|
|
Costs to Provide a grit bin for parish councils. (sites that do not meet NYC criteria for NYC funded bin)
|
£50 |
£51.70 |
|
|
Refills of grit bins per year (includes two refills) |
£75 |
£77.55 |
|
Parks and Countryside Services Fees and Charges
|
Title |
Current price |
Proposed New Price |
Comments |
|
Ripon & Knaresborough Market - Regular Trader - direct debit payment (standard rate effective for 40 weeks per year)* |
£22.75 |
£23.55 |
Including VAT Rounded to assist calculation of min. stall size of 3 metres at £7.85 per metre |
|
Ripon & Knaresborough Market - Regular Trader - direct debit payment (Winter rate effective for 12 weeks per year) * |
£19.00 |
£19.65 |
Including VAT |
|
Ripon & Knaresborough Market - Casual Trader* |
£25.50 |
£26.70 |
Including VAT Rounded to assist calculation of min. stall size of 3 metres at £8.90 per metre |
|
Ripon & Knaresborough Market - New Starter Rate* |
£12.25 |
£12.67 |
Including VAT |
|
Knaresborough Market - Surcharge to provide and erect stall* |
£5.50 |
£5.69 |
Including VAT |
|
Ripon & Knaresborough Market - Small table / hanging space* |
£2.75 |
£2.84 |
Including VAT |
|
Ripon & Knaresborough Market - Electricity* |
£9.75 |
£10.08 |
Including VAT |
|
Ripon & Knaresborough Market - Local charity stall* |
£0.00 |
£0.00 |
Including VAT |
|
Northallerton Market - Regular trader - Monthly direct debit in advance, per metre frontage (min £22.80)* |
£5.50 |
£5.70 |
Including VAT Rounded to assist calculation of min. stall size of 4 metres at £5.70 per metre
|
|
Northallerton Market - Regular trader - Weekly cash, per metre frontage |
£6.10 |
N/A |
This fee has been discontinued |
|
Northallerton Market - Casual trader - Weekly, per metre frontage (min £30.80)* |
£7.45 |
£7.70 |
Including VAT |
|
Northallerton Market – Electricity Charge* |
£5.00 |
£5.17 |
Including VAT |
|
Thirsk Market - Regular trader - Monthly direct debit in advance, per metre frontage (min £20.40)* |
£4.90 |
£5.10 |
Including VAT Rounded to assist calculation of min. stall size of 4 metres at £5.10 per metre |
|
Thirsk Market - Regular trader - Weekly cash, per metre frontage (min £22.80)* |
£5.50 |
N/A |
This fee has been discontinued |
|
Thirsk Market - Casual trader - Weekly, per metre frontage (min £27.40)* |
£6.60 |
£6.85 |
Including VAT |
|
Thirsk Market - Casual trader - bank holiday - Weekly cash per metre frontage (min £27.40)* |
£6.60 |
N/A |
This fee has been discontinued as it is the same as the weekly rate |
|
Helmsley & Pickering Markets – pitch hire* |
£29.00 |
£29.99 |
Including VAT |
|
Helmsley & Pickering Markets - Vehicle* |
£7.30 |
£7.55 |
Including VAT |
|
Scarborough Indoor Market* Main Floor, Regular Trader Fee per m2, per annum |
£222.00 |
£229.55 |
Including VAT |
|
Scarborough Indoor Market* Mezzanine Floor – Regular Trader, per m2 month* |
£186.00 |
£192.32 |
Including VAT |
|
Scarborough Indoor Market Vaults – Regular Trader – indoor per unit per month* |
£36.40 |
£67.64 |
Including VAT |
|
Scarborough Indoor Market Vaults – Regular Trader – outdoor per unit per week* |
£39.50 |
£40.84 |
Including VAT |
|
Scarborough Indoor Market Storage Unit per week* |
£8.90 |
£9.20 |
Including VAT |
|
Scarborough Indoor Market Seating Area per week* |
£12.45 |
£12.87 |
Including VAT |
|
Scarborough Indoor Market Car Parking per week* |
£8.30 |
£8.58 |
Including VAT |
|
Scarborough Indoor Market Electrical Rate (supplier charge plus) per month * |
£4.70 |
£4.86 |
Including VAT |
|
Scarborough Indoor Market Application Fee* |
£190.00 |
£196.46 |
Including VAT |
|
Scarborough Indoor Market Hall Hire* |
£POA |
£250 |
Including VAT |
|
Whitby Market Pitch hire – (single 3mx3m) – Tuesday / Saturday* |
£17.00 |
£17.58 |
Including VAT |
|
Whitby Market Pitch hire – (single 3mx3m) – Sunday* |
£27.00 |
£27.92 |
Including VAT |
|
Scarborough - Farmers Market, Market stall* |
£31.75 |
£32.83 |
Including VAT |
|
Scarborough - Farmers Market, Commercial Sale of a Vehicle on the Highway (for period up to sale)* |
£32.90 |
£34.02 |
Including VAT |
|
Hanging Basket Scheme - Harrogate Area, Subsidised rate* |
£96.00 |
£99.26 |
Including VAT |
|
Hanging Basket Scheme - Harrogate Area, Non-subsidised rate* |
£157.00 |
£162.34 |
Including VAT |
|
Allotments – Harrogate Area, Standard rental (300 square yards / 250m2) |
£78.65 |
£81.32 |
VAT Exempt Allotment holders are entitled to one year’s notice for any price changes so prices are for 2026/27and 2027/28 respectively. |
|
Allotments – Harrogate Area, Senior citizens |
£42.15 |
£43.58 |
VAT Exempt Allotment holders are entitled to one year’s notice for any price changes so prices are for 2026/27 and 2027/28 respectively. |
|
Allotments – Harrogate Area, Water charges |
£14.75 |
£15.25 |
Zero rated VAT Allotment holders are entitled to one year’s notice for any price changes so prices are for 2026/27 and 2027/28 respectively. |
|
Allotments – Scarborough Area, Standard Rental |
£60.30 |
£62.35 |
VAT Exempt Allotment holders are entitled to one year’s notice for any price changes so prices are for 2026/27 and 2027/28 respectively. |
|
Allotments – Craven Area, Standard Rental Rental price dependant on plot size. |
£41.15- £82.00 |
£42.55-£84.79 |
VAT Exempt Allotment holders are entitled to one year’s notice for any price changes so prices are for 2026/27 and 2027/28 respectively. |
|
Community Event Hire Charge - Small event (up to 999) |
£0.00 |
£0.00 |
|
|
Community Event Hire Charge - Medium event (1000 - 1999) |
£0.00 |
£0.00 |
|
|
Community Event Hire Charge - Large event (2000+) |
£0.00 |
£0.00 |
|
|
Community Event Application Fee (non-refundable) Small event (up to 999 attendees) |
£126.00 |
£130.28 |
Excludes VAT Per event |
|
Community Event Application Fee (non-refundable) (1000 attendees and over) |
£186.00 |
£192.32 |
Excludes VAT Per event |
|
Community Event Bond (refundable) Small event (up to 999) |
£500.00 |
£517.00 |
Outside scope of VAT Per event |
|
Community Event Bond (refundable) Medium event (1000 - 1999) |
£1,210 |
£1,251 |
Outside scope of VAT Per event |
|
Community Event Bond (refundable) Large event (2000+) |
POA |
POA |
Outside scope of VAT Per event, price on application. |
|
Commercial Hire - Premium location event fees (Harrogate Stray and town centre open spaces) - Harrogate Area |
£1,425 |
£1,473.45 |
Excludes VAT Per day |
|
Commercial Hire - Premium locations application fee Harrogate Area only (non-refundable) |
£186.00 |
£192.32 |
Excludes VAT Per day |
|
Commercial Hire - All other locations |
£670.00 |
£692.76 |
Excludes VAT Per day |
|
Commercial Application Fee All other locations (non-refundable) |
£186.00 |
£192.32 |
Excludes VAT Per day |
|
Commercial Hire – Bond (refundable) |
£550 - £5,000 |
£569 -£5,170 |
Excludes VAT Per day |
|
Professional Fees - Event Management Plan due diligence |
£237.50 |
£245.58 |
Excludes VAT Per event |
|
Professional Fees - On site event supervision |
£465.00 |
£480.81 |
Excludes VAT Per day |
|
Tennis - Court hire |
£8.30 |
£8.60 |
Including VAT Per court, per hour |
|
Tennis - Hire of racket |
£3.00 |
£3.10 |
Including VAT Per racket |
|
Tennis - Hire of balls |
£2.50 |
£2.60 |
Including VAT Per set (6) |
|
Flat Green Bowls - Adult |
£4.90 |
£5.10 |
Including VAT Per game / hour |
|
Flat Green Bowls - Child / Concession |
£3.20 |
£3.30 |
Including VAT Per game / hour |
|
Flat Green Bowls - Season ticket, Adult |
£84.00 |
£86.86 |
Including VAT, Per season |
|
Flat Green Bowls - Season ticket, Child / Concession |
£42.50 |
£43.95 |
Including VAT Per season |
|
Flat Green Bowls - Hire of woods |
£2.80 |
£2.90 |
Including VAT Per set |
|
Bowls – Selby Park |
£36.00 |
£37.22 |
Per event |
|
Crown Green Bowls - Adult |
£4.90 |
£5.10 |
Including VAT Per game / hour |
|
Crown Green Bowls - Child / Concession |
£3.20 |
£3.30 |
Including VAT Per game / hour |
|
Crown Green Bowls - Hire of Woods |
£2.80 |
£2.90 |
Including VAT Per set |
|
Pitch & Putt Golf – Adult |
£6.10 |
£6.30 |
Including VAT Per round |
|
Pitch & Putt Golf – Child / Concession |
£3.80 |
£3.95 |
Including VAT Per round |
|
Pitch & Putt Golf – Season Ticket, Adult |
£235.50 |
£243.50 |
Including VAT Per season |
|
Pitch & Putt Golf – Season Ticket, Child / Concession |
£126.00 |
£130.28 |
Including VAT Per season |
|
Pitch & Putt Golf – Book of 10 sessions, Adult |
£53.00 |
£54.80 |
Including VAT Per book |
|
Pitch & Putt Golf –Book of 10 sessions, Child / Concession |
£29.50 |
£30.50 |
Including VAT Per book |
|
Putting, Continental Golf, Table Tennis (30mins), Disc Golf, Adult. |
£3.60 |
£3.80 |
Including VAT Rounded to assist cash handling |
|
Putting, Continental Golf, Table Tennis (30mins), Disc Golf, Child / Concession |
£2.80 |
£2.90 |
Including VAT Per round |
|
Putting, Continental Golf, Table Tennis (30mins), Disc Golf, Adult – try 2 activities |
£5.50 |
£5.70 |
Including VAT Per round |
|
Putting, Continental Golf, Table Tennis (30mins), Disc Golf, Child / Concession – try 2 activities |
£4.20 |
N/A |
This fee has been discontinued |
|
General Charges (games) – lost golf ball |
£1.80 |
N/A |
This fee has been discontinued |
|
General Charges (games) – lost tennis ball |
£2.80 |
N/A |
This fee has been discontinued |
|
General Charges (games) – lost / broken club or racket |
£20.50 |
N/A |
This fee has been discontinued |
|
General Charges (games) – lost / broken disc |
£7.50 |
£7.75 |
Including VAT Per disc |
|
Football pitch hire football – Harrogate Area, Stray. Senior teams. |
£337.50 |
£348.98 |
VAT Exempt Per season Charge only applicable to changing facilities |
|
Football pitch hire football – Harrogate Area; Cats Field, Crimple Meadow, Fysche Hall, Harlow Hill, Hydro, Queen Ethelburgas. Senior teams. |
£306.50 |
£316.92 |
VAT Exempt Per season No changing facilities except Harlow Hill |
|
Football pitch hire football – Harrogate Area; Cats Field, Crimple Meadow, Fysche Hall, Harlow Hill, Hydro, Queen Ethelburgas. Junior teams. |
£172.40 |
£178.26 |
VAT Exempt Per season No changing facilities except Harlow Hill |
|
Football pitch hire football – Harrogate Area; Hookstone Road and Hay-a-Park. Senior teams. |
£542.00 |
£560.43 |
VAT Exempt Per season With changing facilities |
|
Football pitch hire football – Harrogate Area; Hookstone Road and Hay-a-Park. Junior teams. |
£395.20 |
£408.69 |
VAT Exempt Per season With changing facilities |
|
Football pitch hire football – Harrogate Area, Killinghall Moor and Camp Close. Senior teams. |
£816.30 |
£844.05 |
VAT Exempt Per season With changing facilities |
|
Football pitch hire football – Harrogate Area; Killinghall Moor and Camp Close. Junior teams. |
£395.30 |
£408.70 |
VAT Exempt Per season With changing facilities |
|
Football pitch hire football – Harrogate Area, Hell Wath, Ripon. Junior teams. |
£172.35 |
£178.21 |
VAT Exempt Per season With changing facilities - upon agreement with Ripon City. |
|
Football pitch hire one-off / ad hoc – Harrogate Area. Killinghall Moor / Camp Close / Hell Wath (with changing facility)
|
£85.40 |
£88.30 |
Excludes VAT Per match |
|
Football pitch hire one-off / ad hoc – Harrogate Area. Killinghall Moor / Camp Close / Hell Wath (without changing facility) |
£49.50 |
£51.18 |
Excludes VAT Per match |
|
One off hire for Killinghall Moor Meeting Room only |
£49.50 |
£51.18 |
VAT Exempt Per half day |
|
Public Path Order Charges - Initial advice and site visit
|
£591.34
|
£611.44 |
|
|
Public Path Order Charges - Registration
|
£81.22 |
£83.98 |
|
|
Public Path Order Charges - Informal Consultation
|
£916.00
|
£947.15 |
|
|
Public Path Order Charges - Initial liaison with objectors
|
£939.22 |
£971.16 |
|
|
Public Path Order Charges - Making a public path order
|
£2,272.77
|
£2350.05 |
|
|
Public Path Order Charges - Each additional path
|
£220.33
|
£227.82 |
|
|
Public Path Order Charges - Liaison with objectors
|
£1,693.00
|
£1750.56 |
|
|
Public Path Order Charges - Confirming an unopposed Public Path Order
|
£498.56
|
£515.51 |
|
|
Public Path Order Charges - Based on
the charges above an unopposed PPO will cost an applicant
|
£4,359.89
|
£4508.13 |
|
|
New S31(6) submission - registration fee
|
£440.66
|
£455.65 |
|
|
New S31(6) submission - registration of extra blocks of land (per block up to £168.50 2025/26, £173.89 2026/27)
|
£34.78
|
£35.96 |
|
|
Renewal of a current submission with no changes to be made
|
£69.56
|
£71.92 |
|
|
Renewal of a current submission where changes are being made
|
£301.45
|
£311.70 |
|
*All items marked with an asterisk indicate these charges may be subject to a review in year.
|
Initial equality impact assessment screening form This form records an equality screening process to determine the relevance of equality to a proposal, and a decision whether or not a full EIA would be appropriate or proportionate.
|
|||||||
|
Directorate |
Environment |
||||||
|
Service area |
Highways and Infrastructure |
||||||
|
Proposal being screened |
Fees and Charges 2026/27 review |
||||||
|
Officer(s) carrying out screening |
James Gilroy |
||||||
|
What are you proposing to do? |
Review fees and charges for Highways and Infrastructure in time for 2026/27 financial year |
||||||
|
Why are you proposing this? What are the desired outcomes? |
Corporate requirement to review fees and charges on an annual basis, in order to ensure full cost recovery in line with Council Fees and Charges policy agreed November 2022 |
||||||
|
Does the proposal involve a significant commitment or removal of resources? Please give details. |
No |
||||||
|
Impact on people with any of the following protected characteristics as defined by the Equality Act 2010, or NYC’s additional agreed characteristics As part of this assessment, please consider the following questions: · To what extent is this service used by particular groups of people with protected characteristics? · Does the proposal relate to functions that previous consultation has identified as important? · Do different groups have different needs or experiences in the area the proposal relates to?
If for any characteristic it is considered that there is likely to be an adverse impact or you have ticked ‘Don’t know/no info available’, then a full EIA should be carried out where this is proportionate. You are advised to speak to your directorate representative for advice if you are in any doubt.
|
|||||||
|
Protected characteristic |
Potential for adverse impact |
Don’t know/No info available |
|||||
|
|
Yes |
No |
|||||
|
Age |
|
No |
|
||||
|
Disability |
|
No |
|
||||
|
Sex |
|
No |
|
||||
|
Race |
|
No |
|
||||
|
Sexual orientation |
|
No |
|
||||
|
Gender reassignment |
|
No |
|
||||
|
Religion or belief |
|
No |
|
||||
|
Pregnancy or maternity |
|
No |
|
||||
|
Marriage or civil partnership |
|
No |
|
||||
|
|
|||||||
|
People in rural areas |
|
No |
|
||||
|
People on a low income |
|
No |
|
||||
|
Carer (unpaid family or friend) |
|
No |
|
||||
|
Are from the Armed Forces Community |
|
No |
|
||||
|
Does the proposal relate to an area where there are known inequalities/probable impacts (for example, disabled people’s access to public transport)? Please give details. |
No |
||||||
|
Will the proposal have a significant effect on how other organisations operate? (for example, partners, funding criteria, etc.). Do any of these organisations support people with protected characteristics? Please explain why you have reached this conclusion. |
No |
||||||
|
Decision (Please tick one option) |
EIA not relevant or proportionate: |
ü
|
Continue to full EIA: |
|
|||
|
Reason for decision |
Full EIA not required. Any increase is reflective of the cost of delivering the service and/or in line with the Consumer Price Index inflation rate. All the rates have previously been benchmarked against comparator authorities. |
||||||
|
Signed (Assistant Director or equivalent) |
Barrie Mason |
||||||
|
Date |
03/03/2026 |
||||||
Climate change impact assessment
The purpose of this assessment is to help us understand the likely impacts of our decisions on the environment of North Yorkshire and on our aspiration to achieve net carbon neutrality by 2030, or as close to that date as possible. The intention is to mitigate negative effects and identify projects which will have positive effects.
This document should be completed in consultation with the supporting guidance. The final document will be published as part of the decision making process and should be written in Plain English.
If you have any additional queries which are not covered by the guidance please email climatechange@northyorks.gov.uk
Version 2: amended 11 August 2021
![]() |
|
Title of proposal |
Review of Highways and Infrastructure fees and charges 2026/27 |
|
Brief description of proposal |
Review of Service Fees and Charges to ensure the Council charges the correct rate for its services and achieves full cost recovery |
|
Directorate |
Environment |
|
Service area |
Highways and Infrastructure |
|
Lead officer |
James Gilroy |
|
Names and roles of other people involved in carrying out the impact assessment |
N/A |
|
Date impact assessment started |
20 February 2026 |
|
Options appraisal Were any other options considered in trying to achieve the aim of this project? If so, please give brief details and explain why alternative options were not progressed.
Fees and charges need to be reviewed and where appropriate, revised, in order to reflect the actual cost of services to the Council
|
|
What impact will this proposal have on council budgets? Will it be cost neutral, have increased cost or reduce costs?
Please explain briefly why this will be the result, detailing estimated savings or costs where this is possible.
The review and implementation of the new fees and charges should have a positive effect on council budgets ensuring the correct fee or charge is received for that service. It will be cost neutral
|
|
How will this proposal impact on the environment?
|
Positive impact (Place a X in the box below where relevant) |
No impact (Place a X in the box below where relevant) |
Negative impact (Place a X in the box below where relevant) |
Explain why will it have this effect and over what timescale?
Where possible/relevant please include: · Changes over and above business as usual · Evidence or measurement of effect · Figures for CO2e · Links to relevant documents |
Explain how you plan to mitigate any negative impacts.
|
Explain how you plan to improve any positive outcomes as far as possible. |
|
|
Minimise greenhouse gas emissions e.g. reducing emissions from travel, increasing energy efficiencies etc.
|
Emissions from travel |
|
Y |
|
|
|
|
|
Emissions from construction |
|
Y |
|
|
|
|
|
|
Emissions from running of buildings |
|
Y |
|
|
|
|
|
|
Emissions from data storage |
|
Y |
|
|
|
|
|
|
Other |
|
Y |
|
|
|
|
|
|
Minimise waste: Reduce, reuse, recycle and compost e.g. reducing use of single use plastic |
|
Y |
|
|
|
|
|
|
Reduce water consumption |
|
Y |
|
|
|
|
|
|
Minimise pollution (including air, land, water, light and noise)
|
|
Y |
|
|
|
|
|
|
Ensure resilience to the effects of climate change e.g. reducing flood risk, mitigating effects of drier, hotter summers |
|
Y |
|
|
|
|
|
|
Enhance conservation and wildlife
|
|
Y |
|
|
|
|
|
|
Safeguard the distinctive characteristics, features and special qualities of North Yorkshire’s landscape
|
|
Y |
|
|
|
|
|
|
Other (please state below)
|
|
Y |
|
|
|
|
|
|
Are there any recognised good practice environmental standards in relation to this proposal? If so, please detail how this proposal meets those standards. |
|
N/A
|
|
Summary Summarise the findings of your impact assessment, including impacts, the recommendation in relation to addressing impacts, including any legal advice, and next steps. This summary should be used as part of the report to the decision maker.
No climate change impact is considered to arise as a result of the proposed Highways and Transportation Fees and Charges.
|
|
Sign off section
This climate change impact assessment was completed by:
Authorised by relevant Assistant Director (signature): Barrie Mason
Date: 03/03/2026 |