Decision details
Highways Capital Programme 2021-22
Decision Maker: Corporate Director of Business and Environmental Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The following schemes agreed for delivery in
the 2021-22 financial year:
- Main Street, Ulleskelf, Selby – replace or relocate
existing drainage pipe to reduce highway flooding and potential
impact on nearby residential properties (est cost
£35,000)
- St John’s Road, Scarborough – investigate and make
safe a void located beneath the carriageway surface (est cost
£12,000)
Alternative options considered:
To allow the additional schemes which need to
be delivered in-year for operational reasons, to be programmed and
delivered within the current financial year 2021/22.
Publication date: 04/10/2021
Date of decision: 24/09/2021