Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To undertake a procurement exercise for the
replacement of a prefabricated classroom unit at Bishop Monkton
Primary CE School with traditional build.
This project will replace a prefabricated
classroom unit at Bishop Monkton CE Primary School with a
traditional build classroom. The project is being funded from the
Children and Young People’s Service capital programme. The
procurement exercise is programmed to run between January and
February 2022. The scheme is programmed to commence on site in May
2022 and will complete in September 2022.
None.
Publication date: 29/11/2021
Date of decision: 23/11/2021