Highways Capital Programme 2021-2022

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To approve the proposed changes to the 2021/22 programme with the exception of the proposed scheme on Bogs Lane in Starbeck, which will now be retained for delivery in 2021/22.

Reasons for the decision:

Due to the reduced level of capital funding revived for 2021/2022 alongside the value of slipped schemes moved from 2020/2021 into 2021/2022, it was necessary to re-profile the 21/22 programme and move some schemes planned for delivery in to future years.

Alternative options considered:

N/a

Publication date: 01/04/2021

Date of decision: 26/03/2021