Decision details
*Republished - no longer subject to call in* Procurement exercise for the replacement of the West Riding 2 class block at Spofforth CE VC Primary School with a new permanent building
Decision Maker: Executive Member for Education, Learning & Skills
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Decision:
To undertake a procurement exercise for the
replacement of the West Riding 2 class block at Spofforth CE VC
Primary School with a new permanent building
Reasons for the decision:
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project is to replace the dilapidated West Riding double
classroom block with a new permanent, traditionally constructed,
two classroom building which incorporates pupil and staff welfare
facilities.
The procurement exercise is programmed to commence during the
Autumn Term utilising the YORbuild framework. The scheme is
programmed to commence on site in March 2021 and will complete
August 2021.
Publication date: 16/04/2021
Date of decision: 13/10/2020