Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To award a construction contract for the
replacement of the gym and changing rooms (following a fire) at
Sherburn High School.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
In 2018 Sherburn High School suffered a fire which caused the
collapse of a building and the loss of the gymnasium, changing
rooms and ancillary facilities. Temporary facilities were arranged
for the school and a scheme has now been developed and a fully
compliant procurement exercise undertaken for the construction
works. The construction work will commence on site in September
2020 and is due for completion in April 2021.
None.
Publication date: 21/04/2021
Date of decision: 24/08/2020