Decision Maker: Corporate Director Children and Young People's Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To abandon the procurement procedure for the
construction of a new primary school on land to the east of Manse
Farm, Knaresborough
The land where the construction of the new
school was to take place is not currently owned by the Council. At
the start of the procurement procedure it was anticipated the land
for the development of the school would be provided to the Council
by the developer in accordance with the S106 Agreement.
Unfortunately, the development of the Manse Farm site has not
progressed as per the developers original programme due to a number
of factors including house sales, build out rates, infrastructure
installation and diversion. In part some of these delays are due to
COVID-19. The developers are therefore not in a position to offer
the site for transfer. The original construction programme cannot
be met and therefore, the procurement exercise must be
abandoned.
Publication date: 21/04/2021
Date of decision: 20/04/2021