*Re-published: call-in no longer applies* Procurement exercise for the refurbishment of the kitchen and pupil toilets at Whitley and Eggborough Community Primary School

Decision Maker: Assistant Director Strategic Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To undertake a procurement exercise for the refurbishment of the kitchen and pupil toilets at Whitley and Eggborough Community Primary School.

Reasons for the decision:

*PLEASE NOTE This decision was originally published on or near the date of the decision and so call in no longer applies. It has been re-published as part of the change in committee management system that we use.*

The scheme is to undertake a refurbishment works to the kitchen and some pupil toilets at Whitley and Eggborough Community Primary School. The procurement exercise is programmed to commence in February 2021 utilising the YORbuild framework. The scheme is programmed to commence on site in July 2021 and is due to complete August 2021.

Alternative options considered:

None.