To undertake a procurement exercise for the
provision of a hygiene room at Staveley Community Primary
School.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project will provide a hygiene room at Staveley Community
Primary School. The procurement exercise is programmed to commence
in March 2021 utilising the YORbuild framework. The scheme is
programmed to commence on site in June 2021 and is due to complete
August 2021.
None.
Publication date: 23/04/2021
Date of decision: 15/12/2020