Decision details

*Re-published: call-in no longer applies* Re: A19 Chapel Haddlesey Funding

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Corporate Director - BES in consultation with the Executive Member for Access authorise funding of £1.165M from the Highways Capital Programme to provide the local contribution for the delivery of the scheme.


Reasons for the decision:

*PLEASE NOTE This decision was originally published on or near the date of the decision and so call in no longer applies. It has been re-published as part of the change in committee management system that we use.*

This enables the schemes to be delivered with minimised impact on the wider Highways Capital Programme.

Publication date: 28/04/2021

Date of decision: 18/12/2020