Decision details

*Re-published: call-in no longer applies* Re: Highways Capital Programme 2018/19

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To approve the additional schemes detailed below for delivery in the 2018/19 financial year.

District, Location, Address, Est Cost/£, Reason for addition.

Scarborough: Boggle Hole, 18,000, Road at risk of further slippage. Works need to be completed before further damage caused by winter tides.

Ryedale: North Grimston, Ludith Road, 30,600, This is a replacement for the Gillamoor Cattle Grid which cannot be delivered this year. Therefore this scheme has a nil net financial effect on the Capital Programme.

Hambleton: Sutton Bank Rockface Works, 60,000, Emergency works identified. It was necessary to complete these works during the annual September closure of this road.


Reasons for the decision:

*PLEASE NOTE This decision was originally published on or near the date of the decision and so call in no longer applies. It has been re-published as part of the change in committee management system that we use.*

The schemes were added to the 2018/19 capital programme as a result the operational reasons detailed in the table above.

Publication date: 10/05/2021

Date of decision: 28/09/2018