Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To award a construction contract for window
replacement works at Ingleton Primary, Settle College,
Knaresborough King James School and Boroughbridge High
School.
Schemes to provide window replacement works
are planned at at Ingleton Primary, Settle College, Knaresborough
King James School and Boroughbridge High School. A fully compliant
competitive procurement exercise has been completed during May
2021utilising the YORbuild framework. The schemes are programmed to
commence on site in August 2021 and are due to complete in
September 2021.
None.
Publication date: 14/06/2021
Date of decision: 10/06/2021