Low Faggergill & Wood House Footbridge Replacement Works - Award of Contract

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Award the contract for Low Faggergill & Wood House Footbridge Replacement Works (Bridge No. 3839 & 3840) to HINKO Construction Ltd for £77,765.00. The works involve the replacement of Low Faggergill and Wood House Footbridge abutments. Collecting new bridge, transport to site and assembly.

Funding for these two bridges is the Area 1 Flood fund 2019/2020 which does not affect the normal Capital or Revenue funding of Footbridges.

Reasons for the decision:

NYCC carried out an open tender procurement exercise, two compliant bids were received and HINKO are the least expensive of the two. The contract is a NEC Engineering and Construction Short Contract. HINKO has undertaken many similar scheme previously for NYCC Bridges and their overall performance is good.

Publication date: 10/09/2021

Date of decision: 10/09/2021