Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To undertake a procurement exercise for the
replacement of the double prefabricated classroom unit at Thirsk
School and Sixth Form College
A scheme to replace a double prefabricated
classroom unit with new provision is planned at Thirsk School and
Sixth Form College. The procurement exercise is programmed to
commence in November 2021 utilising the YORbuild framework. The
scheme is programmed to commence on site in May 2022 and is due to
complete July 2022.
None.
Publication date: 02/11/2021
Date of decision: 02/11/2021