Decision details
Procurement exercise for the creation of an intervention space at Foston CE Primary School
Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To undertake a procurement exercise for the
creation of an intervention space at Foston CE Primary
School.
Reasons for the decision:
This project will create an intervention space
at Foston CE Primary School. The project is being funded from the
Children and Young People’s Service capital programme. The
procurement exercise is programmed to run between January and
February 2022. The scheme is programmed to commence on site in May
2022 and will complete in August 2022.
Alternative options considered:
None.
Publication date: 29/11/2021
Date of decision: 23/11/2021