Decision details
*Re-published: call-in no longer applies* Procurement exercise for the refurbishment of three science laboratories, two prep rooms, food technology and art at Risedale School
Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Decision:
To undertake a procurement exercise for the
refurbishment of three science laboratories, two prep rooms, food
technology and art at Risedale School.
Reasons for the decision:
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project will provide refurbished curriculum facilities at the
school. The scheme comprises of the refurbishment of three science
laboratories, two associated prep rooms, food technology and art
facilities. The procurement exercise is programmed to commence in
March 2021, utilising the YORbuild framework. The scheme is
programmed to commence on site in July 2021 and will complete
September 2021.
Alternative options considered:
None.
Publication date: 28/04/2021
Date of decision: 21/01/2021