Decision details

*re-published: call-in no longer applies* Highways Capital Programme 2019/20 and 2020/21

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Decision:


a. Allocation of the carry-over funding for the Highways Capital Programme for Street Lighting, Bridges and Structures, Integrated Transport and Structural Highway Maintenance for 2019/20;
b. The contribution from the Countywide Civil Parking Enforcement (CPE) surplus for signs and lines for 2019/20/21; and
c. The 2020/21 Highways Capital Programme.

Reasons for the decision:

To allow the capital programme of highway works to be delivered and programmed for 2019/20 and 2020/21.

Publication date: 28/04/2021

Date of decision: 23/08/2019