Re: C4/20/00868/OA-Planning application for alterations to entrance gates and fencing, including widening of access road and installation of 1 no. lighting column 3.6 metres and 1 no. CCTV column on land at Caedmon College Whitby, Prospect Hill, Whit
Decision Maker: Chief Executive Officer
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The Chief Executive Officer has taken all
relevant information into account in exercising his emergency
delegated powers in this matter include considering the views of
the Planning and Regulatory Functions Committee held on 20 July
2021 and agreed the following:-
that the application be approved for the reasons stated below and
in accordance with the conditions outlined in the report, subject
to the following amendments:-
Condition 2 being amended as referred to in the report to reflect
revision C and not B of the Design and Access Statement.
By whom: Richard Flinton, Chief Executive Officer, under emergency
delegated powers and after consultation with the Planning and
Regulatory Functions Committee.
PLEASE NOTE that as a non-executive function, this decision is not
open to call in.
Reasons for the decision:
Under his delegated decision making powers in
the Officers’ Delegation Scheme in the Council’s
Constitution, the Chief Executive Officer has power, in cases of
emergency, to take any decision which could be taken by the
Council, the Executive or a committee.
Following on from the expiry of the Local Authorities and Police
and Crime Panels (Coronavirus) (Flexibility of Local Authority and
Police and Crime Panel Meetings) (England and Wales) Regulations
2020 (“the 2020 Regulations”), which allowed for
committee meetings to be held remotely, the County Council resolved
at its meeting on 5 May 2021 that, for the present time, in light
of the continuing Covid-19 pandemic circumstances, remote
live-broadcast committee meetings should continue, with any formal
decisions required being taken by the Chief Executive Officer under
his emergency decision making powers and after consultation with
other Officers and Members as appropriate and after taking into
account any views of the relevant Committee Members.
The Chief Executive Officer has taken all relevant information into
account in exercising his emergency delegated powers in this
matter, including:-
• considering the views of the Planning and Regulatory
Functions Committee held on 20 July 2021.
• There are no material changes as a result of the revised
NPPF dated 20 July 2021
The reasons for the decision in this matter are as follows:
• The principle of the proposal improves the amenity of the
college and improves safety and safeguarding features at the school
which have been highlighted by Ofsted as an area in which the
college needs to improve on;
• The proposed development would have a negligible impact upon
the amenity of any
local residents, visual or otherwise;
• The proposed development would have a negligible impact on
the local highway
area;
• The proposed development is in-compliance with the
principles of the NPPF, the
PPG and with Policy SD1, DEC 1, DEC 4, HC8, HC10, ENV 5 and INF 3
of the
Scarborough Borough Local Plan (2017)
Subject to Condition 2 being amended as referred to in the to
reflect revision C and not B of the Design and Access
Statement
Alternative options considered:
N/A.
Publication date: 29/07/2021