Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
•To allow completion of Heads of terms between NYC, DIO and MOD
•To finalise the governance around the collaborative working and Land Transfer of the LUF boundary to NYC control/ownership.
•Sign off and agreement by Executive member required to facilitate the completion of these documents.
Considered – A report of the Corporate Director for
Community Development seeking authority to enter into a Collaboration Agreement and Lease with the
Defence Infrastructure Organisation on the terms principally contained within
the report; and delegate agreement of the final terms of the collaboration
agreement and lease, including the final determination of the Defence
Infrastructure Organisation’s match funding contributions by way of capital
costs and land value as well as securing sufficient on-going maintenance costs
for the completed Levelling Up Fund (LUF) project from the Defence
Infrastructure Organisation’s subsequent commercial and residential
developments
Councillor Derek Bastiman introduced the report, confirming He drew attention to the previous acceptance
of the capital grant funding in May 2023, the meetings and discussions that had
taken place to date, the terms of the Collaboration Agreement and Lease, and
the ongoing procurement process to seek an operator for the Community and
Enterprise facility, all as detailed in the report.
As a local Councillor, Councillor Carl Les welcomed the project and as there
were no arising questions, it was
Resolved – That:
i. A
Collaboration Agreement and Lease be entered into with the Defence Infrastructure
Organisation to facilitate the delivery of the LUF Catterick Garrison Towns
Centre Regeneration project on the terms principally contained within the
report; and
ii. The
Council would take responsibility for delivering any section 106 obligations
associated with its planning application in respect of the LUF project; and
iii. Authority
be delegated to the Corporate Director of Community Development in discussion
with the Executive Member for Open to Business and Corporate Director of
Resources to agree the final terms of a Collaboration Agreement and Lease with
the Defence Infrastructure Organisation; and
iv. The delegation would include the final
determination of the DIO’s match funding contributions by way of capital costs
and land value as well as securing sufficient on-going maintenance costs for
the completed LUF project from the DIO’s subsequent commercial and residential
developments and comprised in Phase 2.
Report author: David Caulfield
Publication date: 12/01/2024
Date of decision: 12/12/2023
Decided at meeting: 12/12/2023 - Executive
Accompanying Documents: