Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To provide an update on the New Settlement (Maltkiln) DPD following the withdrawal of land within the proposed boundary, and set out recommended next steps
Considered – A report of the Corporate Director for
Community Development providing
an update on the New Settlement (Maltkiln) Development Plan Document (DPD)
following the withdrawal of previously available land within the proposed
boundary and seeking in principle approval to use of the Council’s Compulsory
Purchase Powers to support the delivery of Maltkiln if an agreement cannot be
reached with the owners of the land outlined.
Councillor Derek Bastiman introduced the report and welcomed the public
participants to the meeting and their submissions, as follows:
1. Clare Beckett
– Chair of Whixley Parish Council
‘Whixley Parish
Council (WPC) has been involved in the development of the Maltkiln proposals
for many years, including participating in the Community Liaison Group. WPC has
made a number of representations at different stages of the process including
most recently providing detailed comments on the HBC DPD document in November 2022.
Separately we have made representations on the developers planning application
19/00017EIAMAJ, most recently detailed comments on the Transport Assessment –
WPC Document dated January 2023.
There are some
very significant infrastructure requirements to deliver Maltkiln. HBC attempted
to list and cost these in the DPD (Section 11 – Delivery and Phasing) but the
information in this section was full of omissions, inconsistencies and errors
(WPC comments on DPD Page 9). The
developer’s own highway advisor concluded that the A59 between the A1(M) and
Maltkiln would need to be widened to a dual carriageway (Developer’s Transport
Assessment Para 8.10 onwards) but that the developer would not be able to fund
it. A widening scheme for the A59 is not included in the HBC list of
infrastructure projects in the DPD.
The developer’s
highway advisor made errors in their assessment of the capacity of the existing
A59 (WPC Document January 2023) which means the dual carriageway scheme will be
required much sooner in the build out of the development. Using the correct
calculations A59 widening may also be required on the east side of Maltkiln.
A key element of
the development is to provide a new bridge over the railway to replace the
existing Cattal level crossing. Network Rail have full control over the
provision of this bridge and WPC do not believe the costs and risks of this
have ever been properly quantified.
Infrastructure requirements of this scale will require funding from the
public sector. NYC have now concluded CPO and by implication public money is
likely to required just to assemble the land required for the comprehensive
development envisaged in HBC’s Local Plan.
There must be
sufficient doubt over the availability of public funds of this scale to mean that
NYC should question whether delivery of Maltkiln is a viable prospect and
whether it’s a sensible use of public money to proceed with the DPD
process. WPC would like to ask the
executive members whether they have been sufficiently briefed over the viability
of the scheme, including the implications of recent cost rises, to have
confidence that proceeding with the DPD is appropriate?
WPC would
conclude that the further uncertainty CPO brings is a reason to halt the
process and consider the need for Maltkiln within the wider development of
NYC’s new development plan.’
Councillor Derek Bastiman voiced appreciation for the positive and
constructive engagement from Whixley Parish Council on the DPD to date and in
response to the submission reiterated that the proposed recommendation aimed to
get the DPD to the next stage of plan-making - an independent examination by
the secretary of state, in order to allow full scrutiny of the viability and
infrastructure demands.
He noted the Parish Council was correct in
that there were large infrastructure demands to deliver Maltkiln. Whilst a note
was published detailing viability work undertaken so far, the Council had since
commissioned specialist advice to look at the viability of the scheme which
showed that Maltkiln was a viable scheme. He also confirmed that if the DPD
proceeded to examination, the advice would be published and submitted for
consideration at the examination in public.
2. Kevin Bramley
– Parish Councillor for Hunsingore Walshford with Great Ribston &
Cattal Parish Council
‘Residents are concerned that the
New Settlement proposal could be becoming North Yorkshires HS2. Concern has been expressed
by some residents as to the timing of the report to Committee and the short period in which to raise questions or pass comment.
Clashing with the festive period.
Have the Councillors been
informed, interrogated and established the costs to date and considered those going forward
of pursuing the proposal
for a New
Settlement including separately identified costs of other public bodies which have been involved in the process? (All using Tax
Payers money).
The above question is raised
because views have been expressed that
the overall project is not viable. Affordable housing requirements have been reduced through the process (which had been agreed presumably on viability grounds)
This reduction took place prior to the inflation run, hike in interest rates and economic shocks of
more recent times.
Local gossip suggests Oakgate Yorkshire Ltd the applicants of planning application 19/00017/ EIAMAJ and site promoters
(Caddick Group as they are now referred to by the
Council) do not have control of the majority of the site. Indeed it was noted in one of the community
Liaison group meetings that although
engagement has taken place with Network Rail on infrastructure issues
the "elephant in the
room" of ransom and
land agreements had not been advanced as negotiations with Network Rail
are difficult.
Cllr Derek Bastiman thanked Mr Bramley for
his submission and noted that the Maltkiln Community Liaison Group (which includes
Hunsingore Walshford with Great Ribston & Cattal Parish Council)
had been notified of the broad timings of decision making on Maltkiln and that
the report had been published in line with the Council’s committee
procedures. He confirmed the viability work showed Maltkiln was a viable scheme without public sector
intervention, and that the Council had always been open about viability being a
challenge for most new settlements and larger scale schemes. He suggested it
was unlikely that 40% affordable housing would be achieved on all phases of
development, but given it was a very long-term scheme, suggested that later
phases would be expected to contribute more affordable homes. He also noted the
significant benefits to delivering new settlements and providing facilities and
infrastructure in a holistic and well-planned way.
In terms of land availability, Councillor Derek Bastiman
confirmed the Council was satisfied that the test of delivery set out in
national policy (i.e. that there is a reasonable prospect of the site being
delivered) could be met subject to the decision before Executive. He also drew attention to the regular discussions
between the Council and Network Rail and confirmed that whilst the finer
details of the shared value payments had yet to be concluded, the Council did
not believe that was a barrier to delivery. Shared value payments had been
accounted for in viability appraisal work.
3. Richard
Holliday an Associate at Carter Jonas speaking on behalf of their client Mr
Dent of The Wheelhouse, Hunsinggore, Wetherby, LS22 5HY (Landowner)
‘We refer to
the recently published Executive report which seeks an in-principal approval
that the Council use its CPO powers to support delivery of the above New
Settlement. Given the Council’s requirements for lodging a representation 3
working days before the Executive Committee, we have not had much time to read
and consider the paper. However, there are a number of comments we wish to make
at this stage of the process which should be drawn to the attention of Members
taking the decision and which are set out below.
We are surprised
to see a recommendation to progress with compulsory acquisition given the stage
the proposals for the New Settlement have reached. The key concern is that it
cannot be demonstrated that there is a compelling case in the public interest
and, therefore, it is not possible to take forward a CPO. Even an in principle
resolution is premature at this stage.
A key reason
given in the report for needing an in-principal decision is that a landowner
(and here we are assuming you are referring to our client) decided not to renew
their agreement with the site promoter, the Caddick Group. The Caddick Group
had an option to purchase land owned by our client which they decided not to
exercise and which they let expire. It is difficult to see how CPO can be
justified, even in-principle, in circumstances where the land could have been
acquired by agreement. Related to this is that there are no identifiable
boundaries to the New Settlement yet and, therefore, it is not possible to
determine the extent of land needed to deliver the proposed New Settlement. If
the boundaries cannot be ascertained, how is it possible for negotiations to
take place under the threat of CPO given the Council is unable to confirm what
land is actually required from each landowner and, therefore, what is needed
for the proposed development? Compulsory
purchase is not a generic tool and there must be certainty for those affected,
even at the in-principal stage.
We note that the
Council asserts that the Caddick Group controls the majority of the land
required. We should be grateful if details of this can be made available as we
were not aware that the Council had secured the majority of the rest of the
land that it needs? We also note that the report refers to both landowner and
landowners but has not clarified the number of landowners which are affected by
CPO. We would request greater transparency on this point.
So far as the DPD
is concerned, the Executive report refers to a draft which has been submitted
to the Planning Inspectorate but not progressed. Our understanding is that a
DPD consultation was undertaken (both in 2020 and 2022), but there is no
document with any status upon which any development proposals are underpinned.
Therefore, again, there appears to be no basis for taking forward proposals for
development and there is too much uncertainty as to whether, in planning terms,
a New Settlement at Hammerton/Cattal is needed, viable and deliverable. It is,
therefore, far too early to even contemplate CPO as a means of acquiring land.
We would ask
Members not to endorse the recommendation. The proper approach, as outlined in
CPO policy, is for the Council to engage in meaningful negotiations with our
client when it has reached the stage of knowing what land is required and it
has a proper basis for moving forward with the New Settlement proposals.’
Councillor Derek Bastiman thanked Mr Holliday for his comments and
confirmed that Council officers had been in dialogue with Mr Dent and their
advisor for some time. He noted the potential use of CPO had arisen because it
had become apparent to the Council that land previously understood to be
available was now not. He also confirmed the Council was still keen to continue
meaningful dialogue with the landowner and site promoters to ensure that a
negotiated solution could be achieved thereby avoiding the need to resort to
compulsory purchase. He stressed that
the recommendation in this report was not seeking authority to use CPO powers,
rather it was an in principal decision to do so should a negotiated settlement
not be possible.
Councillor Bastiman drew attention to the report and confirmed the
Council believed the proposed boundary for Maltkiln (including all of the land
shown in Appendix A to the report) represented the best option to deliver a
sustainable new settlement that met the requirements of the adopted Harrogate
District Local Plan, and a viable proposition as shown by the work undertaken
so far.
Finally, he noted the DPD had not been submitted to the Secretary of
State for examination in public following a decision by the former Harrogate
Borough Council to publish a final Draft for consultation and submit
thereafter. That submission had been paused to allow further conversations to
take place with Mr Dent.
To clarify the intention of the report, Barry Khan Assistant Chief Executive
(Legal & Democratic Services) drew attention to a proposed revision to recommendation
(i) in the report as follows:
i)
That the Executive approve in principle Recommend
to Full Council that a Compulsory Purchase Order can be is pursued
as a mechanism to deliver a new settlement at Maltkiln if an agreement with
landowners cannot be reached.
Mr Holliday confirmed his client had further
queries to discuss and therefore would welcome more time to negotiate with the
Council, and his view was that at this stage a CPO was a drastic tool to use
particularly as previous negotiations halted as a result of the decisions of
the developer.
4. Paul Townsend
– Chair of Kirk Hammerton Parish Council
‘I represent
Kirk Hammerton Parish Council. Cattal Station and a significant part of the
development land is in our Parish. It’s true that we were opposed to the
original choice of location, but over the past 3-4 years we have spent a lot of
time assisting the Council in developing the Maltkiln proposals. For example,
the idea of the link road to the A168 was ours. Please don’t write us off as
NIMBYs. On the other hand we are, most definitely, local taxpayers.
North
Yorkshire/Harrogate officials have put a lot of effort into this scheme. They
created the policy framework and appointed an experienced promoter to manage
the development risks and deliver the scheme. Unfortunately, the developer has
been unable to do that successfully and the briefing paper concludes that the
project is undeliverable, as things stand. Does that mean the Council should
now intervene and invest its own capital? We think not. It’s time to draw a
line and move on.
We would urge
the Executive to be very cautious indeed before considering the use of
taxpayers’ money, even in principle. At a time when many authorities are on the
verge of bankruptcy, does NYC really have capital available to invest in
speculative development projects? If so, please can it be used for less
glamorous but more appropriate purposes, like fixing the holes in our roads.
There are many
risks which could still derail this project. Complex highways works, high costs
of meeting renewable energy and environmental standards are examples. The
developer has not resolved these challenges. This is not a scheme which just
requires NYC to stump up some cash to allow construction of new houses to
proceed. The elephant in the room is that no agreement exists, even in
principle, with Network Rail for the construction of a road bridge over the
railway, a fundamental element of the scheme and which is to be built on the
land NYC would be purchasing using CPO. The developer has been quite open in
describing this as a “ransom position” for Network Rail. The ransom terms will
only increase once it becomes known that the Council has purchased land that
will be worthless if the scheme doesn’t proceed.
You will be told
that none of this matters because there’s no commitment to spend money at this
stage. So what is the purpose of resolving “in principle” to use CPO powers?
Simply to intimidate the landowner to agree to the developer’s terms, or we’ll
impose a CPO? Surely that’s not how a reputable public authority behaves?
Two final
points, because time is short – Firstly, investing in the scheme will create an
obvious conflict of interest for NYC as Planning Authority. It will be
impossible to maintain the appearance of acting objectively when dealing with
future planning applications if it has an interest in the successful delivery of
the development. And
second, there is a flaw in the soundness of the planning process which is not
mentioned in the briefing paper. The options appraisal of three alternative
locations will not be finalised until the DPD is adopted. The appraisal
concluded (several years ago) that there was little to choose between the three
sites. That was before it became clear that 42% of the development land at
Maltkiln was unavailable and required a CPO. The conclusion would surely be
different now. The risk of challenge to the soundness of the process should be
addressed before any question of investing taxpayers’ money arises. All things considered, we simply have to
conclude, unfortunately, that the project has reached the end of the road.’
Councillor Derek Bastiman thanked Mr Townsend, and all the other parish
councils that formed part of the Community Liaison Group for their time and
effort engaging with the DPD process. He noted the group had given valued input
into the DPD and many of the policies reflected their suggestions and
aspirations. He also noted that the group had assisted with ensuring
constructive participation with the DPD within the wider community.
He went on the confirm that delivering any new settlement would almost
certainly be a challenge and Officers liaison with other authorities delivering
new settlements had confirmed this to be the case. That said, he was pleased to
note the work undertaken to date showed that Maltkiln was a viable scheme, and
that officers believed the framework within the proposed DPD still remained the
most sustainable option when considered against the other options considered
previously.
He accepted the railway line presented a challenge but also a great
opportunity to create a place where sustainable travel was truly at the heart
of the settlement. He noted Network Rail had always supported a new settlement
in this location and that dialogue had continued with them throughout the DPD
process. He also suggested that if the
DPD progressed successfully through an examination in public and was adopted;
and if agreement with the landowners could not be reached; then there were
still a variety of options available to the Council moving forward some of
which would not pose significant risk or cost to the Council.
Finally, he noted that whilst the Council needed to meet a number of
demands and provide value for money for its taxpayers, it also had a duty to
provide high quality homes to meet the needs of current and future residents.
He stated Maltkiln represented an opportunity to deliver a minimum of 3,000
homes in a way which could offer a high quality of life, offering services,
facilities and green space within walking distance for its residents and easy
rail access to other places.
Councillor Arnold Warneken also addressed the Executive and suggested the
amended recommendation was unnecessary given that every Council had the power
to use CPOs and therefore an ‘in principle’ decision to use one in the case of
Maltkiln was superfluous. He also questioned
whether the Council had spoken directly with the affected landowners and whether
more pressure should be placed on the developers to progress the matter to
address the hiatus they had created. He
suggested there should also have been greater communication with the Parish
Councils and with the local Councillors.
In response Councillor Derek Bastiman confirmed that officer had been
having regular discussions with the landowners and developers. He noted his willingness to attend Parish
Council meetings and the importance of the Liaison Group. He also confirmed that feedback from the
Group had led to changes to the plans.
He drew attention to a number of questions that Councillor Warneken had
submitted outside of the meeting and confirmed that responses to those
questions would be provided in writing.
Barry Khan Assistant Chief Executive (Legal
& Democratic Services) confirmed that prior to being submitted for
examination, the Council’s DPD would go to full Council for approval. He
stressed that an assessment had been made which confirmed this was a suitable
and sustainable development and that the purpose of the recommendation for an
in principle decision regarding the potential use of a CPO was to show the
Council’s serious support for the proposed development.
Councillor Derek Bastiman went on to draw
attention to the background to the scheme as detailed in the report, the vision
for Maltkiln, the consultation undertaken to draft the DPD, and the next steps.
Councillor Simon Myers welcomed the
progression of the plans for the development recognising a new settlement would
help address the county’s housing needs.
He also acknowledged the benefits gained historically by Local
Authorities from using CPOs to demolish slums and build social housing. He therefore gave his support to the revised
recommendation.
As there were no further questions, it was
Resolved – That it be approved in principle
that a Compulsory Purchase Order can be pursued as a mechanism to deliver a new
settlement at Maltkiln if an agreement with landowners cannot be reached.
Report author: Rachael May
Publication date: 12/01/2024
Date of decision: 12/12/2023
Decided at meeting: 12/12/2023 - Executive
Accompanying Documents: