Decision Maker: Corporate Director of Business and Environmental Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Award of the contract for Oakbeck Bridge
replacement scheme to Howard Civil Engineering for
£1,067,929.93.
The scheme is from the Capital Budget and has exceeded the 21/22
allocated budget of £750,000.00. The remaining
£317,929.90 will be funded from the 22/23 Capital Budget as
the scheme will be undertaken during both financial years.
Not open to call-in.
Oakbeck Road bridge and Oakbeck footbridge are
in need of urgent attention that needs to be carried out this
financial year as a priority sooner rather than later to prevent
further structural integrity of both bridges. This new scheme will
remove and replace both bridges installing a new one wider concrete
structure allowing for 3no. Road lanes and 2no. Footpaths which
will cater for the increasing traffic and future developments
including allowing abnormal load vehicles over the road
bridge.
Out of the 3 tenders that were returned, Howard Civil Engineering
returned a complaint tender with the cheapest cost to carry out the
scheme works.
To allow for the funding to be split over two financial years the
scheme on-site start date will be pushed back to January 2022. This
is to by-pass the Christmas period and works shutdown period
resulting in no traffic congestion issues around the A59 to A61
roundabout in Harrogate.
Leaving the existing structures is not an
option. The footbridge has been repaired previously and the repairs
have failed, the structure is now considered to be at the end of
its life and is beyond economic repair. The existing road bridge
was temporarily repaired and strengthening would be difficult in
the location and achieving load carrying capacity would also be
difficult.
Publication date: 06/10/2021
Date of decision: 05/10/2021