Award a construction contract for the remodelling of accommodation to form SEN provision at The Skipton Academy

Decision Maker: Assistant Director Strategic Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To award a construction contract to Pacy & Wheatley at a value of £324,674.62 for the remodelling of accommodation to form SEN provision at The Skipton Academy.

Reasons for the decision:

The competitive procurement exercise was undertaken during April and May 2022 utilising the YORbuild framework. The scheme is programmed to commence on site in August 2022 and is due to complete in September 2022.

Alternative options considered:

None.

Publication date: 18/07/2022