Decision details

Whitby Swing Bridge Steel and Resurfacing works - Award of Contract

Decision Maker: Corporate Director of Business and Environmental Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Award of the contract for Whitby Swing Bridge steel works and resurfacing for £88,614.80 to PBS Construction.


Reasons for the decision:

An open procurement exercise was carried out. The planned resurfacing works to Whitby Swing Bridge are not only to replace the surfacing which has started to fail, but also to reduce heat transfer through the existing surfacing into the bridge structure which will reduce the amount of expansion on hot summer days, this will be done by using a lighter coloured surfacing material.

Publication date: 08/09/2022

Date of decision: 25/07/2022