Decision Maker: Executive Member for Education, Learning & Skills
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
That having undertaken the required
preliminary checks, the Executive Member resolved that the four key
issues listed in section 9 of the report have been satisfied and
there can be a determination of the proposals as follows:
That the following proposal be determined:
i) To cease to maintain Kell Bank CE VC Primary School with effect
from 31 August 2021.
ii) To extend the catchment area of Masham CE VA Primary School
with effect from 1 September 2021 to serve the area currently
served by Kell Bank CE VC Primary School.
The number of children at Kell Bank CE VC
Primary School has been falling over the past few years. At the
beginning of September 2019, there were 15 pupils on roll in the
school. This was well below the capacity of the school which could
accommodate around 50 pupils. In September 2020 the school had 6
pupils remaining on roll.
On 15 September 2020 the full governing body met to discuss the
future of Kell Bank School CE VC Primary School. They resolved
unanimously to ask NYCC to consult on the potential closure of the
school from 31 August 2021 in light of the current pupil numbers
and the lack of progress in achieving any alternative structural
solutions.
On 26 January 2021 the Executive approved the publication of
statutory proposals to close Kell Bank CE VC Primary School with
effect from 31 August 2021. This followed careful consideration of
the responses to public consultation carried out by the Children
and Young People’s Service. The statutory proposals and
public notices were published on 5 February 2021, giving 4 weeks
until 5 March 2021 for representations to be made. Following the
publication of the Statutory Notices, one comment was received by
the end of the notice period on 5 March 2021. A anonymised copy of
this comment can be found at Appendix C to the report.
In considering proposals, the Executive Member
for Schools (as there were no objections received during the
representation period), as Decision Maker can decide to:
• reject the proposals;
• approve the proposals with a modification;
• approve the proposals subject to them meeting a specific
condition.
Publication date: 23/03/2021
Date of decision: 23/03/2021
Effective from: 31/03/2021