Procurement exercise for a classroom and toilet extension at Foston Primary School

Decision Maker: Assistant Director Strategic Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To undertake a procurement exercise for a classroom and toilet extension at Foston Primary School.

Reasons for the decision:

The scheme forms part of the Children and Young People’s Service School condition programme. The procurement process is programmed to begin in February 2023. The work is programmed to commence on site in May 2023, with completion in September 2023.

Alternative options considered:

None.

Publication date: 09/01/2023

Date of decision: 09/01/2023