Decision details

Great Ouseburn Community Primary School

Decision Maker: Assistant Director Strategic Resources

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To undertake a procurement exercise for the replacement of a single prefabricated unit with a double prefabricated classroom unit at Great Ouseburn Primary School

Decision:

To undertake a procurement exercise for the replacement of a single prefabricated classroom unit with a double prefabricated classroom unit at Great Ouseburn Community Primary School.

Reasons for the decision:

The scheme forms part of the Children and Young People’s Service School condition programme. The procurement process is programmed to begin in January 2023. The work is programmed to commence on site in July 2023, with completion in September 2023.

Alternative options considered:

None.

Publication date: 12/01/2023

Date of decision: 11/01/2023

Effective from: 20/01/2023