Decision Maker: Corporate Director of Business and Environmental Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The approval for 25 additional new schemes up
to the value of £1.38M, as detailed in Appendix 1 of the
report to be included within the Highways Capital Forward Programme
(HCFP).
As implementation of an earlier Key Decision on 27 May 2022 and as
a non key decision by an officer, is NOT open to call in.
To allow design and development work to
commence on the schemes added into the Highways Capital Forward
Programme.
To grant approval for the schemes to be delivered in future
years.
Publication date: 03/05/2023
Date of decision: 27/03/2023
Accompanying Documents: