Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To undertake a procurement exercise for the
refurbishment of pupil toilet facilities at Carlton in Snaith
Primary School.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project will provide refurbished toilet facilities at Carlton
in Snaith Primary School. The procurement exercise is programmed to
commence in November 2020 utilising the YORbuild framework. The
scheme is programmed to commence on site in April 2021 and is due
to complete August 2021.
None.
Publication date: 22/04/2021
Date of decision: 29/10/2020