To undertake a procurement exercise for the
provision of a hygiene room and ramp at Sutton in Craven Church of
England Voluntary Controlled Primary School.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project will provide a hygiene room and ramp at Sutton in
Craven Church of England Voluntary Controlled Primary School. The
procurement exercise is programmed to commence in March 2021
utilising the YORbuild framework. The scheme is programmed to
commence on site in July 2021 and is due to complete August
2021.