Decision details

Highways Capital Programme 2024-2025

Decision Maker: Corporate Director of Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Authorisation of two additional schemes to the Highways Capital Forward Programme (HCFP) for Structural Highway Maintenance identified since the last Highways Capital Programme report dated 25 August 2023 at a combined value of £115k for

• A59 Kex Gill, Blubberhouses – landslip and monitoring

Reasons for the decision:

To allow design and development work to commence on the schemes added into the Highways Capital forward programme (HCFP) and for schemes to be delivered in the financial year 2024/25.

[Not a Key Decision as implemented as part of an earlier decision]

Alternative options considered:

N/a

Publication date: 26/02/2024

Date of decision: 22/02/2024

Accompanying Documents: