Long Gill East Bridge Repairs - Award of Contract

Decision Maker: Corporate Director of Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Award of contract for Long Gill East Bridge Repairs for £115,678.00 to Thomas Armstrong (Construction) Limited.

Reasons for the decision:

Following an open procurement exercise, Thomas Armstrong proved to be the lowest price compliant bid for the scheme. Thomas Armstrong has undertaken several high-profile schemes for the council and produced excellent results.



Alternative options considered:

Delaying the scheme until next year runs the risk of further deterioration of the bridge structure. Widening the bridge would significantly increase the cost of repairs, this project. is considered the most cost-effective use of the bridge repair budget.


Publication date: 01/11/2024

Date of decision: 30/10/2024