Highways Capital Programme

Decision Maker: Corporate Director of Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The additions to the Highways Capital Forward Programme for Structural Highway Maintenance identified since the last Highways Capital Programme report dated 12 September 2024 are approved:

Area 3
A171 Normanby Bends Drainage, Hawsker - £35,000
U2413 Stoupe Brow Landslip, Fylingdales Moor – £200,000

Reasons for the decision:

The recommendations will enable Council officers, working alongside NYH and partner organisations to develop designs and deliver the schemes listed in Appendix A with expected delivery start dates within the 2024/25 financial year.


Alternative options considered:

None considered

Publication date: 05/11/2024

Date of decision: 01/11/2024