To authorise the acceptance of the Public
Sector Decarbonisation Scheme Phase 4 grant, following confirmation
that NYC’s application has been successful.
This funding stream is being made available by the Government to
provide public sector bodies with access to funding to support heat
decarbonisation schemes in their properties.
Following successful confirmation of
NYC’s grant application to the to the Public Sector
Decarbonisation Scheme Phase 4 a decision has been made to accept
the grant of £536 928, to support the delivery of carbon
reduction measures at Nidderdale Leisure Centre. The work will be
undertaken between the date of acceptance of the offer and the 31st
March 2028 in line with the grant T&Cs.
Applicants are expected to contribute to the costs of the project
what would have been spent on a like for like replacement of a
gas/oil boiler, therefore the council’s contribution is
expected to be £103,755 from the Property service
budget.
The application to submit an application for the Public Sector
Decarbonisation Fund Phase 4 was a Key Decision and entered on the
Forward Plan in June 2024, with a Decision made to submit the
application on the 31st October 2024.
The Report around acceptance of the grant was circulated as soon as
possible after the grant offer letter was received with a request
made and agreed in relation to call in exception as the grant
funding offer letter needs to be signed within 10 business days
from the date of the letter (7th March 2025) or the grant funding
will expire.