Decision Maker: Corporate Director of Business and Environmental Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
i) Subject to ii) below, the Contract Period,
assessed as part of the HMC 2012 Evaluation Panel (29 June 2015) is
to remain unchanged and will expire on 31 March 2021.
ii) The Corporate Director in consultation with the BES Executive
Members agrees that by 30 September 2015:
a. Negotiations with Ringway about the revisions to the new
Performance Management Framework have been concluded.
b. The systems development phase for the new working arrangements
for minor works has been completed.
c. There is a satisfactory conclusion to the discussions with
Ringway relating to the Value for Money Review in respect of urban
grass cutting.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
Highway Maintenance Contract (HMC 2012)
In accordance with the contract documents, the Contract Period is
determined by the performance of the Contractor (Ringway) against
the Contract Performance Indicators (CPIs).
During the contract, the Contract Period may be adjusted by none, 1
or 2 years, between a minimum of 6 years and a maximum of 10
years.
Following a thorough assessment of Ringway’s performance, the
HMC 2012 Evaluation Panel decided that:
the Contract Period is not affected by the performance levels on
the basis of the improved performance compared with the previous
year
Publication date: 11/05/2021