To undertake a procurement exercise for the
replacement of the HORSA kitchen and dining facilities with new
provision at Burton Salmon Primary Schools
To undertake a procurement exercise for the
replacement of the kitchen and dining facilities, and refurbishment
of pupil toilets, at Burton Salmon Primary School.
This project will provide replacement kitchen
and dining facilities and includes for the refurbishment of some of
the pupils toilets. The project is being funded from the Children
and Young People’s Service capital programme. The procurement
exercise is programmed to run between December 2021 and January
2022. The scheme is programmed to commence on site in June 2022 and
will complete in August 2022.
None
Publication date: 25/11/2021
Date of decision: 23/11/2021
Effective from: 03/12/2021