Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To undertake a procurement exercise for the
replacement of two prefabricated classroom units with new provision
at Sleights CE VC Primary School
To undertake a procurement exercise for the
replacement of two prefabricated classroom units and associated
external works at Sleights CE Primary School
This project will replace two prefabricated
classroom units, along with associated external works at Sleights
CE Primary School. The project is being funded from the Children
and Young People’s Service capital programme. The procurement
exercise is programmed to run between January and February 2022.
The scheme is programmed to commence on site in June 2022 and will
complete in August 2022.
None
Publication date: 25/11/2021
Date of decision: 23/11/2021
Effective from: 03/12/2021