Decision Maker: Assistant Director Strategic Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To undertake a procurement exercise for the
replacement of the prefabricated classroom unit with a single class
extension, new corridor and associated facilities at Wavell Infant
and Nursery, and Wavell Junior Schools.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
This project will replace the prefabricated classroom unit with a
single class extension, new corridor and associated facilities. The
procurement exercise is programmed to commence in December 2020
utilising the YORbuild framework. The scheme is programmed to
commence on site in April 2021 and is due to complete August
2021.
None.
Publication date: 21/04/2021
Date of decision: 29/10/2020