Decision Maker: Assistant Director - Travel, Environmental and Countryside Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Approval has been given to progress with the
design and implementation of Option 1 (Two mini Roundabouts) as an
Improvement scheme at Bond End Junction, to introduce Air Quality
benefits to the designated Air Quality Management Area.
Approval has been given to share the results of the Air Quality
modelling work and recommendations with Harrogate Borough
Council’s Air Quality Officer Group, with a request that
further complimentary measures to address air quality at the
junction should be included on future Air Quality Action
Plans.
*PLEASE NOTE This decision was originally
published on or near the date of the decision and so call in no
longer applies. It has been re-published as part of the change in
committee management system that we use.*
To introduce a Junction Improvement scheme at the Bond End
Junction, that will present the greatest opportunity for
improvement to local air quality.
Further options in addition to the recommended
option were considered and discounted in line with the submitted
report.
Publication date: 22/04/2021
Date of decision: 26/01/2018