Decision Maker: Assistant Director - Property, Procurement & Commercial
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To seek approval to undertake a procurement
exercise for the replacement of a HORSA unit with a double
prefabricated classroom unit at Boroughbridge Primary
School.
To undertake a procurement exercise for the
demolition of a HORSA unit and replacement with a double
prefabricated classroom unit at Boroughbridge Primary
School.
A competitive procurement exercise will be
undertaken between February and March 2024. The scheme is
programmed to commence on site in July 2024 and complete in
September 2024.
None given.
Publication date: 31/01/2024
Date of decision: 30/01/2024
Effective from: 08/02/2024