Award a construction contract for drainage, heating and associated planned maintenance works at Welburn Hall School

Decision Maker: Assistant Director - Property, Procurement & Commercial

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To award a construction contract to Walter Thompson Ltd at a value of £4,157,539.24 for drainage, heating and associated planned maintenance works at Welburn Hall School.

* this decision is exempt from call in because it is implementing an earlier key decision to procure which was subject to call in.

Reasons for the decision:

A competitive procurement exercise was undertaken between October 2023 and March 2024. The scheme is programmed to commence on site in August 2024 and complete in June 2025.

Alternative options considered:

N/A

Publication date: 16/05/2024

Date of decision: 07/05/2024