Decision Maker: Corporate Director of Environment
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To seek authorisation to award the second
stage of a construction contract to Jackson Civil Engineering
Limited to carry out the refurbishment works to Filey Sea Wall,
following the issue of a transparency notice.
Jackson Civil Engineering had previously been awarded the first
design stage of the works by Scarborough Borough Council.
Approval to enter into the second stage of the
construction contract to Jackson Civil Engineering Limited to carry
out the works to the Filey sea defences.
To address concerns relating to the integrity
of the existing sea defences and to ensure the longevity of the
coastal erosion in Filey, ensuring the progression of an essential
coastal maintenance project that has been ongoing since
2021.
To not award the second stage of construction
to Jacksons would mean:
• Jacksons have worked through and resolved these issues with
the Council and the benefit of this would be lost
• the contract is a design and build contract. Jacksons retain
the risk liability of the design which would be lost if an
alternative contractor were to be procured
• an alternative contractor would not accept the design risk
of someone else’s design and the risk would then rest with
the Council for any design changes
• to have to re-tender will cause a significant delay and mean
works will not start on site this summer. The EA are expecting the
expenditure of the grant and delivery of the benefits this summer.
There is no guarantee the grant will be maintained and rolled over
to the next financial year next Summer
• Stage 1 of the project requires the contractor to obtain all
necessary consents including planning permission and the Marine
Management Organisation (MMO) licences. The MMO Licence is method
specific to Jacksons and may be required to be resubmitted. The
application decision period is 13 weeks and could only be submitted
following procurement of a new contractor. The length of time lost
would again push the works into Summer 2025
Publication date: 18/07/2024
Effective from: 26/07/2024