Decision Maker: Corporate Director of Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To seek approval for an application for
recoverable grant funding from the Brownfield, Infrastructure and
Land Fund (BIL) to allow early provision of infrastructure on the
West Harrogate project. The funding will be put towards delivery
transport and education schemes identified through the West
Harrogate planning applications.
Approval from the Corporate Director Resources
(sub-delegated to the Assistant Director Resources) in consultation
with the Executive Member for Finance and Resources and the
Executive Member for Open to Business to authorise the submission
of an application for BIL (Brownfield, Infrastructure and Land)
grant funding in the amount of £6,780,994.
To allow officers to continue collaborative
dialogue with the Homes England funding team to secure early
infrastructure delivery on the West Harrogate project.
Not securing the BIL fund recoverable grant
will impact on the pace of delivery for the on-site primary schools
and off-site transport mitigation. Provision of the infrastructure
will have to wait for s106 payments to accumulate through housing
sales and completions. An alternative would be to seek the
applicants to fund larger upfront payments, this is likely to stall
delivery of the housing sites as developers struggle to source
financing terms. It could lead to viability difficulties for
developers which in turn risks challenges to s106 provisions.
A further alternative would be for the education and transport
teams to draw from Council reserves to cover the early
infrastructure provision. This will be paid back through collection
of s106 commuted sums over time but is considered undesirable due
to other considerable pressures on Council budget.
Publication date: 21/03/2025
Date of decision: 21/03/2025
Effective from: 01/04/2025
Accompanying Documents: