Recommendations:
The
Executive are asked to approve that:
i. A consultation process be undertaken in
relation to the pausing of residential provision at Welburn
Hall for a two year period from September 2023
ii.
Planning
permission be sought to install temporary classroom
provision on site
iii. The local authority will not install temporary
accommodation for residential operation
Additional documents:
Minutes:
Considered: A report of the Corporate Director for Children
& Young People Services providing a brief overview of the building challenges
in relation to Welburn Hall Special school, seeking approval for a set of
initial decisions in relation to the school (in light of the major challenges
that have been identified), and discussing the longer-term strategic plans and
investment decisions that will need to be developed and routed back through the
Executive in Spring 2023.
County Councillor Annabel Wilkinson introduced
the report and drew attention to the heating system challenges and the need to
consider a more effective way forward.
She noted the plans to consult with families and thanked officers for
their work and for the report.
As Members had no questions, it was
Resolved – That:
i. A consultation process be undertaken in
relation to the pausing of residential provision at Welburn Hall for a two year
period from September 2023
ii. Planning permission be sought to install
temporary classroom provision on site
iii. The local
authority will not install temporary accommodation for residential operation