Report of the Head of Development Management – Community Development Services
Minutes:
The Head of Development Management – Community Development Services sought determination of a planning application for the construction of a temporary wellsite for the appraisal of gas, including drilling operation, proppant squeeze and flow testing operation and site restoration, land east of the Mill Yard, Burniston Mill, Coastal Road, Burniston, Scarborough, YO13 0DB on behalf of Europa Oil and Gas Limited.
The Development Service Manager, David Walker began by confirming the position in respect of the communication earlier that week from the government that following third party representations, the Secretary of State was considering whether the proposal should be re-screened because of changes in the planning application since his previous decision taken some months ago that the application did not require an Environmental Statement. Mr Walker reminded the committee that notwithstanding the Secretary of State’s previous decision, the applicant had submitted an Environmental Statement in support of the application and that officers continued to regard the contents of the submitted statement to be appropriate in scope and detail. Officers’ advice was therefore that should the committee reach a position at the meeting to determine the application, that this be a ’minded to’ resolution pending the decision of the Secretary of State. Should the government’s decision have a material bearing on the committee’s resolution requiring, say, further information from the applicant, then the application would be resubmitted to the committee for determination. Should the government’s decision not affect the committee’s resolution, then the formal decision of the committee would be issued.
The planning officer then presented the application by first outlining the location of the proposed development and its four phases: site construction; drilling phase; testing and proppant squeeze; and decommissioning and restoration. The planning officer then provided an update to the report since the publication of the agenda in respect of the requirement within the Levelling-Up and Regeneration Legislation (LURA) legislation for planning applications to ‘seek to further the purposes’ of the National Parks. Members were reminded that the committee report clearly recognised the proximity of the site to the National Park and its setting and treated impacts on the Park as a material consideration throughout the assessment. The North York Moors National Park Authority after consultation on the proposal concluded that the proposal would not lead to unacceptable harm to the statutory purposes of the National Park, nor conflict with Minerals and Waste Joint Plan policies intended to protect the Park and its setting. In assessing the development the planning authority had not relied on the ‘no harm’ conclusions of the National Park but had actively added conditions which furthered the Park’s purposes protecting the visual landscape, protecting dark skies with a sensitive lighting scheme and protection of the Cleveland Way and Cinder Track with minor/negligible impacts. In addition, Biodiversity Net Gain requirements secured a net gain from the development which would be required to be monitored for 30 years, going further than harm avoidance and positively contributing to the area, with the site required to be restored after the three-year period of the development. It was therefore considered the report demonstrated a reasonable pro-active approach that satisfied the LURA obligation of seeking to further the statutory purposes of the National Park and in this instance the conditions and requirements of the application mitigated/limited/enhanced the proposal’s effects on the National Park’s statutory purposes.
Following the update to the report, the planning officer explained the key planning considerations which had shaped the officer recommendation. These considerations covered the full range of environmental, technical, and amenity issues raised by consultees, statutory bodies, interest groups and the public as set out in the report. Finally, the planning officer moved to the report’s conclusions and recommendation. It was considered that any potential impacts on the environment could be controlled and addressed through the imposition of appropriate planning conditions and this would ensure that the council could control and monitor the site. The development was supported by the local and national policies which comprised the Development Plan and it was therefore recommended that planning permission be granted subject to the conditions outlined in the report.
In accordance with public speaking arrangements at planning committee, the following speakers then addressed the committee with their allotted times:
Objecting to the application:
|
Professor Chris Garforth (Chair of the Steering Group of Frack Free Coastal Communities and Katie Atkinson (Planning Consultant) |
5 minutes |
|
Councillor Helen Bore (Newby and Scalby Town Council) |
5 minutes |
|
Councillor Karen Fanthorpe (Cloughton Parish Council) |
5 minutes |
|
Councillor Richard Parsons (Burniston Parish Council) |
5 minutes |
|
Councillor Derek Bastiman (North Yorkshire Council – division councillor) |
5 minutes |
|
Councillor Rich Maw (North Yorkshire Council) |
5 minutes |
|
Councillor Steve Mason (North Yorkshire Council) |
5 minutes |
Summary of issues raised:
·
Significant
concern about risk of induced earthquakes with no site-specific seismic survey
or compelling evidence provided to show risks could be managed. Presence of
known faults, recent cliff falls, and unstable coastal geology highlighted.
·
The
proposal constituted hydraulic fracturing under the Minerals and Waste Joint
Plan and conflicted with multiple local and national planning policies,
including those protecting heritage coasts, the National Park setting, and
precautionary principles.
·
Regarded
as inappropriate industrialisation of a sensitive
rural and heritage coast landscape, visible from public rights of way, the
coast path, and the North York Moors National Park, harming landscape
character.
·
Concerns
that the application failed to properly assess downstream greenhouse gas
emissions, conflicted with UK net zero commitments and North Yorkshire’s
climate ambitions, and relied on outdated policy assumptions favouring fossil fuel extraction.
·
Lack
of a Health Impact Assessment despite policy requirements, with concerns about
noise, lighting, air pollution, traffic, mental health impacts, and proximity
to homes, including vulnerable residents.
·
Risks
raised regarding groundwater contamination, chemical proppants left underground, proximity to watercourses, and
insufficient assessment of impacts on coastal ecosystems.
·
Repeated
objections to the claim that the development was temporary, arguing it was the
first stage of a long-term (20+ year) industrial operation, with equipment
retained on site and likely future applications.
·
Criticism
of a ‘salami-slicing’ approach in the report, with impacts assessed
individually rather than considering the overall cumulative effect on the
community and environment.
·
Limited
or no local economic benefit identified, with claims that energy security
benefits were negligible, gas would be sold on global markets, and tourism and
local businesses would be harmed.
·
Doubts
about the applicant’s financial capacity to complete restoration, with calls
for an independently valued restoration bond to protect the public purse.
·
Key
assessments (seismic surveys, environmental and health assessments) were
missing or proposed post-consent.
In support of the application:
|
Paul Foster (agent) |
5 minutes |
|
Alastair Stuart (applicant) |
5 minutes |
|
Jamie McGill (applicant) |
5 minutes |
|
William Holland (applicant) |
5 minutes |
Summary of issues raised:
·
The
application was for a single appraisal borehole over around five weeks,
followed by testing and full restoration to farmland, with no consent for
production or future development.
·
Seismicity,
subsurface operations and well integrity were regulated by other statutory
bodies (Environment Agency, Health and Safety Eexcutive,
North Sea Transition Authority) and were not matters for determination under
this planning application.
·
The
proposal was consistent with national and local planning policy, which allowed
hydrocarbon appraisal where impacts were assessed and appropriately controlled,
with no planning harms outweighing the benefits identified.
·
Potential
impacts such as noise, traffic, lighting, air quality and visual effects had been assessed and could be effectively managed through
planning conditions.
·
The
site was appropriately located based on geological data, with existing access
from the A165 already used by HGVs and natural screening from surrounding
topography reducing visual impact.
·
Any
impacts during drilling (e.g. rig presence, additional vehicle movements,
temporary noise) were short-term, time-limited and reversible.
·
Members
were urged to focus on whether the surface development was acceptable in
planning terms, rather than speculation about future phases, which would
require separate applications and assessments.
·
Evidence
and testimonials were provided from the Wressle site
in Lincolnshire, where similar operations had resulted in minimal disturbance,
effective community relations and local benefits.
·
Speakers
emphasised regulation, monitoring and enforcement as
safeguards, rather than reliance on trust, and committed to transparency and
ongoing community engagement.
·
The
development would support jobs, investment, energy security and reduced
reliance on imported liquefied natural gas, with claims it could displace
higher-carbon imports.
·
This
was a proppant squeeze / low volume operation, distinct from high-volume
hydraulic fracturing associated with Preston New Road, which led to seismic
issues.
Members then proceeded to discuss and ask questions about the officer report and presentations. Questions centred on the following matters:
Geology,
fault lines and seismicity - Members sought clarification on the location of
fault lines, the extent of geological surveys and the potential for seismic
events. Officers advised that while geological and seismic matters were
acknowledged in the report, detailed control and assessment sat primarily with
other regulatory regimes. Members were reminded that the planning authority
must assume those regimes would operate effectively and that seismic monitoring
and controls would be secured through separate consents.
Air quality
and emissions - Members asked detailed questions regarding nitrogen oxides,
volatile organic compounds, particulates and the potential for odour and fugitive releases. Officers confirmed that the
submitted assessments had been reviewed with Environmental Health colleagues
and were considered robust. It was explained that detailed air quality
monitoring and management arrangements would be secured through
pre-commencement planning conditions.
Noise, lighting
and amenity - Members queried operational noise levels, 24-hour working during
specific phases, light emissions from the rig and flare stack, and the impact
on residential amenity and dark skies. Officers
confirmed that noise limits, monitoring and management would be controlled by
condition, that 24-hour working was operationally
necessary for limited phases, and that a lighting scheme would be required and
could involve consultation with relevant bodies such as the National Park
Authority.
Restoration
and duration - Members sought clarification on the programme
of works, gaps between phases, and restoration
timescales. Officers explained that although the operational phases totalled approximately 37 weeks, the permission allowed
flexibility within a maximum three-year period, after which restoration would
be required in accordance with approved schemes.
Groundwater
and the Environment Agency - Members questioned the Environment Agency’s
initial objection and its subsequent withdrawal. Officers explained the
discussions undertaken, the conditions proposed to address groundwater
protection and confirmed that development could not commence unless the
required method statements were approved in consultation with the EA.
Public
health and other consultees - Members raised concerns regarding public health
input and the role of statutory consultees. Officers confirmed that reliance
had been placed on responses from relevant expert bodies, particularly
Environmental Health, and that health impacts had been considered through the
submitted assessments.
Economic
considerations - Members queried the scale of employment and economic benefit.
Officers advised that the economic benefits were modest and temporary and had
been afforded limited weight in the planning balance.
Heritage
coast and landscape - Members questioned whether the proposal constituted major
development within the Heritage Coast and the weight given to landscape impact,
particularly in light of a previous decision by the
local planning authority to refuse an application for wind turbines at the same
location. Officers confirmed that, while impacts were acknowledged, the
development was considered temporary and reversible, and this had informed the
recommendation.
During the
discussion, it was moved, seconded and approved that any determination by the
committee would be by a recorded vote.
Members
then turned to reaching a determination of the application. Discussion centred on potential reasons for refusal
covering the following six areas:
Members
then voted to amend the motion before them by removing Reason 6. Seismic risk
on the advice of the Head of Legal Property, Planning and Environment that this
reason would not be defendable by the local planning authority should the
committee’s decision be appealed.
Decision:
That the committee be MINDED TO REFUSE planning permission for the following reasons with the final wording to be approved by the Head of Development Management in consultation with the Chair and Councillors Brown, Timothy and Warneken.
The development is contrary to:
The
proposal is therefore contrary to:
· MWJP Policy M17(4)(i);
· MWJP Policy D02;
· Scarborough Borough Local Plan
Policy DEC4;
· NPPF paragraph 187(e).
The proposal is therefore contrary to:
The proposal is therefore contrary to:
The proposal is therefore contrary to:
Voting record:
|
Councillor Andy Paraskos (Chair) |
For |
|
Councillor Andy Brown |
For |
|
Councillor Caroline Goodrick |
For |
|
Councillor Hannah Gostlow |
For |
|
Councillor Yvonne Peacock |
For |
|
Councillor Clive Pearson |
For |
|
Councillor Steve Shaw-Wright |
For |
|
Councillor Roberta Swiers |
For |
|
Councillor Neil Swannick |
For |
|
Councillor Andrew Timothy |
For |
|
Councillor Arnold Warneken |
For |
|
Councillor Robert Windass |
Abstain |
Supporting documents: