Ripon Market Place Resurfacing Scheme

13/09/2024 - Ripon Market Place Resurfacing Scheme

i) Approve the proposed change of material from the concrete tegula blocks to an asphalt flexible material to reduce maintenance liabilities and cost, improve the overall look of the Market Place.

ii) Authorise commencement of procurement for the construction works to return the surface to asphalt.

Updates were provided to the Corporate Director of Environment in consultation with the Executive Member for Highways and Transportation regarding this report and associated decision. The decision made is under the provision that neither of these items can commence until appropriate variation of contract with National Lottery Heritage Fund changing the terms and conditions of grant funding from 2000 for the initial Market Place scheme has been obtained.