*Re-published: call-in no longer applies* Re: Highways Capital Programme 2018/19

10/05/2021 - *Re-published: call-in no longer applies* Re: Highways Capital Programme 2018/19

To approve the additional schemes detailed below for delivery in the 2018/19 financial year.

District, Location, Address, Est Cost/£, Reason for addition

Scarborough: Egton Road, Aislaby, 50,000, Road at risk of further slippage. Works need to be completed before further damage caused by winter tides.

Scarborough: Foreshore Road, Scarborough, 17,500, Slight Structural failure of partial retaining wall. Initial investigation required.

Selby: Parkview Drain, Culvert, Thorganby, 65,000, Collapsed culvert under Carriageway near the boundary line with York Council.

A 170 Valley View Culvert, Near Sutton under Whitestonecliff, 40,000, Culvert has twisted out of position risking that the carriageway may be left unsupported and could result in a road closure.