To consider Harrogate TCF project delivery
options and status following quashing of 30th May 23 Executive
decision to implement in light of a Judicial Review legal
challenge.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 23/08/2023
This decision will be taken under urgency procedures.
Reason for urgency:
To mitigate impact upon project milestones, an urgent decision is required to determine project direction and confirmed project status with grant funding bodies.
Anticipated restriction: Part exempt - View reasons
Decision due: 19 Sep 2023 by Executive
Lead member: Executive Member for Highways & Transportation
Lead director: Corporate Director of Environment
Contact: Richard Binks, Head of Major Projects & Infrastructure Email: richard.binks@northyorks.gov.uk Email: richard.binks@northyorks.gov.uk.
Consultation process
Meeting/committee.
Decision record 07/08/23, published 22/08/23.
Consultees
Grant funding bodies WYCA / DFT, Harrogate and
Knaresborough ACC.